¶ … Baseline Without a project baseline, or a projected idea of the project's original "original scope, cost and schedule" it is impossible to assess whether a project is going well or poorly (Ortiz 2008). The baseline must be accurate to be useful and defined before the project is undertaken. Periodically, over the course of the project, the baseline can be referred to, to see if the project is going over budget or over its allotted time. After the project has begun, Earned Value Analysis (EVA) can forecast how much it will cost and how long it will take to complete based upon where it 'in the here and now,' versus the original projected date of completion according to the baseline (Cullen 2010).

Q1b. The baseline can also raise red flags if things are not proceeding according to schedule. If there is no way the baseline can be met, based upon the first several weeks of projects, the issue can be immediately identified and 'flagged'...

...

However, this requires mindful attention to the original baseline on the part of the individuals participating in the project.
Q1c. An accurate baseline is essential. If the baseline is unrealistic, even if the project is being managed well, it might appear as though something is amiss or the project is not being well-handled because it seems as though the milestones are only being met in a very slow and deliberate fashion. If the project baseline is too generous, then the project might seem to be going very well, despite the fact the project is being mismanaged, simply by virtue of the low expectations that were set for it initially.

Q2. Project communication

Q2a. Communication is essential during a project given that quite often specific phases of the project are contingent upon the completion of other phases. The project manager must keep the team well-informed of what…

Sources Used in Documents:

References

Cullen, S. (2010). Earned Value Analysis. WBDG. Retrieved from:

http://www.wbdg.org/resources/value_analysis.php

Importance of communication in project management. (2013). Goal Keeper. Retrieved from:

http://www.goalkeeper.rs/general-blog-the-importance-of-communication-in-project-management
http://www.pmhut.com/the-project-baseline-a-project-management-definition


Cite this Document:

"Baseline Without A Project Baseline Or A" (2014, February 07) Retrieved April 28, 2024, from
https://www.paperdue.com/essay/baseline-without-a-project-baseline-or-182327

"Baseline Without A Project Baseline Or A" 07 February 2014. Web.28 April. 2024. <
https://www.paperdue.com/essay/baseline-without-a-project-baseline-or-182327>

"Baseline Without A Project Baseline Or A", 07 February 2014, Accessed.28 April. 2024,
https://www.paperdue.com/essay/baseline-without-a-project-baseline-or-182327

Related Documents

Project Management-7 What is the difference between a task dependency and a task constraint? The difference between a task dependency and a task constraint is apparent in the time. A task dependency connects two tasks by suggesting that one task will start comparative to another task, whereas a task constraint places the connection directly to a time rather than base it off the time when another task begins (Marmel and Muir, 2007). Give

Starting with the pre-contractual phase, which was for the most part skipped as the EDS teams focused primarily on technologies first, the project lacked the necessary foundation to succeed from a planning standpoint. Focusing on the pre-contractual phase could have also helped to have more clearly defined the SLAs and metrics used for managing the project over the long-term as well (Cross, 2007). With 23 SLAs and 51 metrics,

" (Lavell & Martinelli, 2008) Mark Kozak-Holland emphasized that the most critical aspect of the Great Escape project was risk management. The work of building the tunnels was extremely dangerous -- danger of collapse of the sandy soil and bad air in the tunnels. The airmen had to place a high probability on the Germans discovering the plot owing to the traces of the excavated soil and nosy guards. The

Project Management Accreditation Project Management A project is a temporary group endeavor, with an agreed beginning and duration time frame, organized to produce a unique product, service or result. (PMI 2011) A distinguishing characteristic of a project is that it is progressively detailed as the project is better understood by the people working on it. Another characteristic of a project is that it is not a routine operation, although a project may

In the case of Hurricane Andrew a behavioral analysis was conducted following the hurricane. According to assessment of Hurricane Andrew for Broward and Dade Counties, "The percentage of residents who evacuated (i.e., left their homes to go someplace they believed would be safer) in Andrew varied by proximity to the shoreline. In Broward county 69% left from the Category 1-2 surge zone, and in Dade 71% left from the Category 1

Project Management Understanding the Principles of project management Aims and objectives of project management Project management is widely referred to as the application of the knowledge, tools, skills as well as the available techniques to activities related to projects in order to achieve the objectives of the project. The concept of project management is primary hinged on the need to coordinate, plan as well as control the diverse and highly complex activities