Paper Example Doctorate 1,269 words

Energy Technology Data Centre Migration Work Breakdown

Last reviewed: May 27, 2012 ~7 min read
Abstract

Brian Smith, who is a network administrator at Advanced Energy Technology (AET) has been tasked with moving a large data centre to a new office location in the newly developed industrial complex at the Corvallis International Airport in Corvallis, Oregon. The company provides application as a service product to two hundred thirty five oil jobbers and gasoline companies. As a result, the company can experience no downtime during the transition to the new facility. Any user interruptions from clients could result in lost revenues and damage to the company's reputation as a reliable IT company in the industry.

¶ … Energy Technology Data Centre Migration

Work Breakdown Structure

Network Diagram

Critical Tasks (Highlighted)

Milestones

Resources Assigned

Quality

Cost

Reporting

Brian Smith, who is a network administrator at Advanced Energy Technology (AET) has been tasked with moving a large data centre to a new office location in the newly developed industrial complex at the Corvallis International Airport in Corvallis, Oregon. The company provides application as a service product to two hundred thirty five oil jobbers and gasoline companies. As a result, the company can experience no downtime during the transition to the new facility. Any user interruptions from clients could result in lost revenues and damage to the company's reputation as a reliable IT company in the industry.

The scenario in this case dictates the entire focus of the project. Since the data center components must all be moved in a weekend after the new location is prepared then there is not any allowance for error. This coupled with the fact that the organization will not tolerate any inconvenience to the clients makes a successful transfer even more salient. Therefore the most important aspect to this project will undoubtedly be thorough risk management and risk planning. A careful evaluation will have to be conducted by each of the functional representatives as well as a risk contingency plan be prepared to avoid any potential delays.

Work Breakdown Structure

Task Name

Duration

Preliminary Discussions

1 day

Scope Meeting

1 day

Initial Project Planning

2 days

Hire Contractor

5 days

Network Design

10 days

Order Hardware (Ventilation)

15 days

Order Hardware (Racks, Servers, Switches, and Others)

10 days

Order Hardware (Power Supplies)

5 days

Install Ventilation

5 days

Install Racks

15 days

Construction

20 days

Inspection

2 days

Install Power Supplies and Run Cables

5 days

Functional Unit Approval

5 days

Check Voltage

1 day

Install Test Servers

5 days

Batteries, Vents, Test Servers

2 days

Primary Systems Check

1 day

Set Official Date

1 day

Move Network Components

2 days

Network Diagram

Critical Tasks (Highlighted)

Task Name

Duration

Start

Finish

Predecessors

Preliminary Discussions

1 day

Mon 5/28/12

Mon 5/28/12

Scope Meeting

1 day

Tue 5/29/12

Tue 5/29/12

1

Initial Project Planning

2 days

Wed 5/30/12

Thu 5/31/12

2

Hire Contractor

5 days

Fri 6/1/12

Thu 6/7/12

3

Network Design

10 days

Fri 6/1/12

Thu 6/14/12

3

Order Hardware (Ventilation)

15 days

Fri 6/15/12

Thu 7/5/12

5

Order Hardware (Racks, Servers, Switches, and Others)

10 days

Fri 6/15/12

Thu 6/28/12

5

Order Hardware (Power Supplies)

5 days

Fri 6/15/12

Thu 6/21/12

5

Install Ventilation

5 days

Fri 7/6/12

Thu 7/12/12

6,11

Install Racks

15 days

Fri 7/6/12

Thu 7/26/12

7,11

Construction

20 days

Fri 6/8/12

Thu 7/5/12

4

Inspection

2 days

Fri 7/6/12

Mon 7/9/12

11

Install Power Supplies and Run Cables

5 days

Tue 7/10/12

Mon 7/16/12

12

Functional Unit Approval

5 days

Tue 7/17/12

Mon 7/23/12

13

Check Voltage

1 day

Tue 7/17/12

Tue 7/17/12

13

Install Test Servers

5 days

Wed 7/18/12

Tue 7/24/12

15

Batteries, Vents, Test Servers

2 days

Wed 7/25/12

Thu 7/26/12

16

Primary Systems Check

1 day

Fri 7/27/12

Fri 7/27/12

17

Set Official Date

1 day

Mon 7/30/12

Mon 7/30/12

18

Move Network Components

2 days

Tue 7/31/12

Wed 8/1/12

19

Milestones

Planning Complete

Installation and Construction Complete

Testing Complete

Project Completion

Resources Assigned

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Preliminary Discussions

1 day

Mon 5/28/12

Mon 5/28/12

Operations

Scope Meeting

1 day

Tue 5/29/12

Tue 5/29/12

1

Operations

Initial Project Planning

2 days

Wed 5/30/12

Thu 5/31/12

2

Design, Engineering, HR, Operations, Purchasing

Hire Contractor

5 days

Fri 6/1/12

Thu 6/7/12

3

Operations, Purchasing

Network Design

10 days

Fri 6/1/12

Thu 6/14/12

3

Design, Engineering, Operations, Purchasing

Order Hardware (Ventilation)

15 days

Fri 6/15/12

Thu 7/5/12

5

Design, Engineering, Purchasing

Order Hardware (Racks, Servers, Switches, and Others)

10 days

Fri 6/15/12

Thu 6/28/12

5

Design, Engineering, Purchasing

Order Hardware (Power Supplies)

5 days

Fri 6/15/12

Thu 6/21/12

5

Design, Engineering, Purchasing

Install Ventilation

5 days

Fri 7/6/12

Thu 7/12/12

6,11

Engineering

Install Racks

15 days

Fri 7/6/12

Thu 7/26/12

7,11

Engineering

Construction

20 days

Fri 6/8/12

Thu 7/5/12

4

Operations

Inspection

2 days

Fri 7/6/12

Mon 7/9/12

11

Design, Engineering, Operations

Install Power Supplies and Run Cables

5 days

Tue 7/10/12

Mon 7/16/12

12

Engineering

Functional Unit Approval

5 days

Tue 7/17/12

Mon 7/23/12

13

Design, Engineering, Operations

Check Voltage

1 day

Tue 7/17/12

Tue 7/17/12

13

Engineering, Operations

Install Test Servers

5 days

Wed 7/18/12

Tue 7/24/12

15

Engineering

Batteries, Vents, Test Servers

2 days

Wed 7/25/12

Thu 7/26/12

16

Design, Engineering, HR, Operations, Purchasing

Primary Systems Check

1 day

Fri 7/27/12

Fri 7/27/12

17

Engineering, Operations

Set Official Date

1 day

Mon 7/30/12

Mon 7/30/12

18

Engineering, HR, Operations, Purchasing

Move Network Components

2 days

Tue 7/31/12

Wed 8/1/12

19

Engineering, Operations

Quality

To determine some of the critical success factors that might be present in this case a review of the literature was conducted. One study found provided a framework for categorization of critical success factors that was based on an analysis of previous research. These categories were then applied to the case to see what insights might be obtained. These categories include (I) business plan and vision; (2) change management; (3) communication; (4) IT team composition, skills and compensation; (5) management support and championship; (6) project management; (7) system analysis, selection and technical implementation (Nah, 2006).

The vision in this case is fairly straight forward however the business plan is far less clear. Planning, especially risk planning, will likely be a critical success factor in this project. Change management will also play an important role since very few of IT projects are performed exactly as planned. This project will also benefit from the fact that there are only five functional divisions involved; a manageable number. However, the project manager should still have a set communication and change management process so that no deviation fails to be reported.

The next two categories, management support and championship as well as project management, can be adequately condensed into a single category in regards to this discussion. Since the project is vital to the success of the entire operation it is very likely that the project will have management's full support throughout the entire process.

Other critical success factors were also identified early user buy-in. In this project, since operations has been involved from the beginning, it is not likely that there will be a significant amount of end-user resistance. The structure of the project virtually guarantees a "partnership" between operations and the rest of the team (Verville, Bernadas, & Halingten, 2005). Somers and Nelson (2001) also provide a set of additional critical success factors which consists primarily of the use of a steering committee, use of consultants, adequate testing, and ongoing vendor support. In this case it might be prudent for the project management to have items such as the design verified by an independent consultant to ensure that the design is up to par. The experience of a consultant can be a tremendous asset in projects such as these; especially when there is little room for error.

You’re 84% through this paper. Sign up to read the full paper.

Sign Up Now — Instant Access Already a member? Log in
130,000+ paper examples AI writing assistant Citation generator Cancel anytime
Cite This Paper
PaperDue. (2012). Energy Technology Data Centre Migration Work Breakdown. PaperDue. https://www.paperdue.com/essay/energy-technology-data-centre-migration-80321

Always verify citation format against your institution’s current style guide requirements.