Such alerts would allow Sound Transit time to apply extra grout between the tunnel and the apartment building's basement.

6. Output Analysis and Discussion

Here, Sound Transit has taken reasonable and economically feasible precautions to reduce the risk of damage from soil sliding. At this point, the remaining hazards come from uncontrollable environmental factors, such as earthquakes and heavy rainfall, all of which are known to cause landslides and mudslides in the city of Seattle. Another factor which could cause damage to surface property is contractor negligence, for example when a contractor drills in a manner or pace which cumulates in excessive vibration and stress on surface structures.

7. Recommendation of the Improvement

In order to mitigate against uncontrollable environmental factors, Sound Transit should make sure that it has insurance policies which cover "Acts of God" in the event that such events result in property damage. In order to mitigate against contractor negligence, Sound Transit should create procedural guidelines which require regular measurement of soil impact and statements detailing contractor responses to new developments in soil conditions.

Bibliography

Practical Risk Management...

ent 4
PRM 4

http://projects.soundtransit.org/Projects-Home/University-Link.xml; http://projects.soundtransit.org/x1698.xml http://projects.soundtransit.org/Projects-Home/University-Link/Capitol-Hill-Station.xml

University Link fact sheet, available at http://projects.soundtransit.org/Documents/pdf/projects/link/north/ULink/U-LinkFact201105.pdf; Tunnel Boring Machine (TBM) fact sheet, available at http://projects.soundtransit.org/Documents/pdf/projects/link/north/ULink/Fact_TBM_2011.pdf

PRM5-6

PRM 6

http://seattletransitblog.com/2009/08/22/what-worries-me / http://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=4&ved=0CDgQFjAD&url=http%3A%2F%2seattletimes.nwsource.com%2Fhtml%2Flocalnews%2F2017786224_lightrailtunnel19m.html&ei=RcihT5uiItDXiQKY_KCnBw&usg=AFQjCNEXOMa_1eXjDZYHLmE0x17HwocskQ&sig2=foo46kTqgFccdURytNg8Aw

http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html

PRM 6

PRM 17

http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html

RISC 7

RISC 7

http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html?

Sources used in this document:
Bibliography

Practical Risk Management 4

PRM 4

http://projects.soundtransit.org/Projects-Home/University-Link.xml; http://projects.soundtransit.org/x1698.xml http://projects.soundtransit.org/Projects-Home/University-Link/Capitol-Hill-Station.xml

University Link fact sheet, available at http://projects.soundtransit.org/Documents/pdf/projects/link/north/ULink/U-LinkFact201105.pdf; Tunnel Boring Machine (TBM) fact sheet, available at http://projects.soundtransit.org/Documents/pdf/projects/link/north/ULink/Fact_TBM_2011.pdf
http://seattletransitblog.com/2009/08/22/what-worries-me / http://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=4&ved=0CDgQFjAD&url=http%3A%2F%2seattletimes.nwsource.com%2Fhtml%2Flocalnews%2F2017786224_lightrailtunnel19m.html&ei=RcihT5uiItDXiQKY_KCnBw&usg=AFQjCNEXOMa_1eXjDZYHLmE0x17HwocskQ&sig2=foo46kTqgFccdURytNg8Aw
http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html
http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html
http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html?
Cite this Document:
Copy Bibliography Citation

Related Documents

Project Risk Management Plan in Renovating a Kitchen
Words: 3737 Length: 12 Document Type: Research Paper

Effective risk management is crucial for ensuring project success. This is true for not only large, complex projects, but also small and less complex projects such as renovating the kitchen at one’s residence. Kitchen renovation is a project that may involve substantive expenditure, hence the need for proper identification, analysis, and mitigation of the associated risks. Generally, the major risks that may arise during the renovation of the kitchen relate

Effective Risk Management in Projects
Words: 1917 Length: 6 Document Type: Research Paper

Anticipated Implementation Issues and Opportunities Effective risk management is crucial for ensuring project success. This is true for not only large, complex projects, but also small and less complex projects such as renovating the kitchen at one’s residence. Kitchen renovation is a project that may involve substantive expenditure, hence the need for proper identification and mitigation of the associated risks. To this end, it is acknowledged that the major risks associated

Management Chapter 1-The Influence of
Words: 4029 Length: 9 Document Type: Research Paper

Furthermore, the proper selection of the team provides a means of determining general responsibilities for each team member involved. They will need to know the overall scope of their service while also knowing their overall design responsibilities as compared to their peers. In addition, their contracts will be a directly correlated to the contract and specifications of the client involved. This is important as it aligns the motivations of

Managing Homeland Security You Were
Words: 2062 Length: 5 Document Type: Essay

S. DHS "Strategic Plan," 2008, http://www.dhs.gov/xabout/strategicplan/) Realistically acts of terrorism, domestic or foreign are exceedingly rare, though slightly more common than they have been in the past and at least marginally more violent in nature, they occur very, very rarely. (Lewis, 2000, p. 201) Though maintaining serious preparedness the mitigation of natural disasters, most which cannot be avoided is an issue needed to be addressed almost yearly, on both small

Emergency Management and Communications Interoperability
Words: 5291 Length: 18 Document Type: Research Proposal

According to the Congressman, there is a basic lack of interoperability across more than 80% of the United States' first responders. They are not able to communicate with each other, and are therefore also not able to launch adequate rescue operations, particularly during times of large-scale emergencies. According to the report, it was found that at least 121 of the 343 fire fighters who died could have been saved had

NMCI Project Management Need a Prelimary Scope
Words: 1329 Length: 4 Document Type: Essay

NMCI Project Management Need a prelimary scope statement-based NMCI project provided, analyze critique NMCI project term organization handled estimation, handled quality communication. 2.Explain challenges. The NMCI (Navy-Marine Corps Intranet) project was meant to link all the Navy's disparate networks, into a single network operated by one contractor. The project was not well estimated in terms of time and money required to fund the whole project. According to Verton (2002) the contractor EDS (Electronic

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now