Cp-2 Project Performance Report Schedule One Performance Essay

CP-2 Project Performance Report Schedule One

Performance Analysis

Estimate at Completion

Control Plan

Revised Estimate at Completion

Schedule Two

During roughly midway into the CP-2 project, it was found that the project was running ten days behind schedule and it was already over budget. This is due to the fact that several tasks went over budget as well as a sluggish schedule performance. At this point the project manager fully utilized the resources at hand to bring the schedule back into order. Despite meeting the schedule requirements, the project did go over budget by a marginal amount. This was a result of using extra labor to crash some of the activities.

Schedule One

The original project schedule predicted that the project would be completed on December 19 of 2008. However, on October 1, 2008 the project manager found that he was ten days behind schedule as well as over budget. The actual schedule at this point predicted that the project would be completed on January 2nd of the following year instead of the intended date.

Task Mode

WBS

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Fixed Cost

Manually Scheduled

1.25

Grand Opening

1 day

Fri 12/19/08

Fri 12/19/08

Customer

$30,000.00

Figure 3 - Original Schedule

Task Mode

WBS

Task Name

Duration

Start

Finish

Predecessors

...

The cost variance was also nearly a hundred and fifty thousand dollars in the negative also representing the fact that the project was over budget. At this point in the project it was estimated that the total project budget would be slightly under five million dollars and would have a variance at completion of negative five hundred seventy eight thousand dollars.
Task Name

Planned Value - PV (BCWS)

Earned Value - EV (BCWP)

AC (ACWP)

SV

CV

EAC

BAC

VAC

Theme Park Project

$1,511,466.67

$1,111,961.33

$1,257,738.00

($399,505.33)

($145,776.67)

$4,990,316.90

$4,411,920.00

($578,396.90)

Estimate at Completion

The estimate at completion (EAC) of the project on 10/01/08 was $4,999,031. This is based on the schedule that was predicting project completion of January 2nd of 2009. Thus this figure did not account for any of the crash costs that would be necessary to accelerate the schedule…

Cite this Document:

"Cp-2 Project Performance Report Schedule One Performance" (2012, February 26) Retrieved April 20, 2024, from
https://www.paperdue.com/essay/cp-2-project-performance-report-schedule-78277

"Cp-2 Project Performance Report Schedule One Performance" 26 February 2012. Web.20 April. 2024. <
https://www.paperdue.com/essay/cp-2-project-performance-report-schedule-78277>

"Cp-2 Project Performance Report Schedule One Performance", 26 February 2012, Accessed.20 April. 2024,
https://www.paperdue.com/essay/cp-2-project-performance-report-schedule-78277

Related Documents

Product Management Issues Quality of Design, Performance, and TQM -- As manufacturing design and implementation became even more complex, an integrative approach to the end product became necessary. There are many theoretical rubrics for this, but one of the more stable and robust is that of TQM, or Total Quality Management. TQM, like other theories such as Six Sigma, is based on the idea that the quality of the end product

Air Traffic
PAGES 102 WORDS 28110

Air traffic has continued to increase and it now constitutes a considerable proportion of the travelling public. The amount of long-hour flights has increased significantly. Based on the International Civil Aviation authority, air traffic can be anticipated to double amid till 2020. Airline travel, especially over longer distances, makes air travelers vulnerable to numerous facets that will impact their health and well-being. Particularly, the speed with which influenza spreads and

Long-Term Relationship You owner/CEO a large business idea concept phase full production, a short window due robotics machinery department Contract Financing Contract is a form of payment; or rather it is an unauthorized government distribution of funding to a contractor before accepting supply of goods or services offered by the government. Contract financing excludes debit payments, payments for incomplete acceptance or charter or rental payments. This is because payments of invoices on

E-Manufacturing - A New Link
PAGES 60 WORDS 22785

Ayers (2000, p. 4) describes a supply chain as "Life cycle processes supporting physical, information, financial, and knowledge flows for moving products and services from suppliers to end-users." A supply chain can be short, as in the case of a cottage industry, or quite long and complex as in the manufacture, distribution, and sales of automobiles. In fact, the automobile supply chain has its origin in the mining of the

Wireless Broadband Technology
PAGES 50 WORDS 20344

Wireless Broadband Technology Overview of Wireless technology Presently it is quite evident to come across functioning of a sort of wireless technology in the form of mobile phone, a Palm pilot, a smart phone etc. With the inception of fast connectivity in the sphere of commerce it is customary and useful to operate from central locations communicating with the remote branches, conducting conferences in remote places, discussing with every body at every

Employee Motivation in a Pcba
PAGES 64 WORDS 17554

Indeed, effective problem solving in these circumstances often requires high levels of creative collaboration (Richards, 2007a, p. 34). In recognition of this reality, employers consistently name the ability to work together creatively as a primary and crucial skill -- even though many organizations have created cultures that undercut individual and collective creativity. In order to solve this problem there is a need of a comprehensive review of the facility management