¶ … MS Project
What was the original project duration prior to resource leveling? (Week 5 (1) file is the WBS before leveling)
In MS Project, a report was run to find the project's total duration. The total duration of the project before the resources were leveled was 140.73 and this made the expected project completion date April 9th, 2012.
What was the revised project duration after resource leveling? (Week 5 (2) is the WBS after leveling)
After the resources were leveled another report was run. This time the duration was calculated to be 84.75 days with a 55.96 day variance.
Carefully read the resource leveling...
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now