MS Project Resource Leveling Essay

PAGES
1
WORDS
411
Cite
Related Topics:

¶ … MS Project What was the original project duration prior to resource leveling? (Week 5 (1) file is the WBS before leveling)

In MS Project, a report was run to find the project's total duration. The total duration of the project before the resources were leveled was 140.73 and this made the expected project completion date April 9th, 2012.

What was the revised project duration after resource leveling? (Week 5 (2) is the WBS after leveling)

After the resources were leveled another report was run. This time the duration was calculated to be 84.75 days with a 55.96 day variance.

Carefully read the resource leveling...

...

Based on your reading and experience in MS software, why is resource leveling important in schedule development?
Resource leveling is a way to fix resource over allocation. Generally, resources are leveled in two ways (MS Office, 2011):

By delaying a task until the assigned resource has time to work on it.

By splitting a task so that part of a task is done when planned and the rest of it is done later when the assigned resource has time.

Basically, even though task durations may dictate that the project has a certain overall duration, resources may be "double booked" since the resources may be…

Sources Used in Documents:

Works Cited

MS Office. (2011). About Resource Leveling. Retrieved from MS Office: http://office.microsoft.com/en-us/project-help/about-resource-leveling-HP001041939.aspx

Wei, C., Liu, P., & Tsai, Y. (2002). Resource-constrained project management using enhanced theory of constraint. International Journal of Project Management, 561-567.


Cite this Document:

"MS Project Resource Leveling" (2011, October 04) Retrieved April 25, 2024, from
https://www.paperdue.com/essay/ms-project-resource-leveling-116984

"MS Project Resource Leveling" 04 October 2011. Web.25 April. 2024. <
https://www.paperdue.com/essay/ms-project-resource-leveling-116984>

"MS Project Resource Leveling", 04 October 2011, Accessed.25 April. 2024,
https://www.paperdue.com/essay/ms-project-resource-leveling-116984

Related Documents

Thirdly, having the ability to motivate the project team is a characteristic of a project manager. Projects can have ups and downs for the project team. When target dates seem far from reach, having a project manager with the ability to motivate the group by setting smaller goals and giving incentives can improve the team's morale. Communicating when things go well instead of only talking about the negative can

Project Management-7 What is the difference between a task dependency and a task constraint? The difference between a task dependency and a task constraint is apparent in the time. A task dependency connects two tasks by suggesting that one task will start comparative to another task, whereas a task constraint places the connection directly to a time rather than base it off the time when another task begins (Marmel and Muir, 2007). Give