Project Management The baggage handling system (BHS) project is in motion. Initially, our company Boeing Airport Equipment Automated Systems, Inc. (BAE) stipulated that no change requests should be accepted. However, it is proving impossible to ignore the influx of change requests from major stakeholders, namely the airlines. As project manager, I have determined...
Introduction Want to know how to write a rhetorical analysis essay that impresses? You have to understand the power of persuasion. The power of persuasion lies in the ability to influence others' thoughts, feelings, or actions through effective communication. In everyday life, it...
Project Management The baggage handling system (BHS) project is in motion. Initially, our company Boeing Airport Equipment Automated Systems, Inc. (BAE) stipulated that no change requests should be accepted. However, it is proving impossible to ignore the influx of change requests from major stakeholders, namely the airlines. As project manager, I have determined that our policy regarding change requests should itself be changed, from a public relations standpoint.
We cannot risk further isolating core stakeholders, for risk that the entire project fall apart later due to technical, design, conceptual, or implementation flaws that might arise. It is my duty as project manager to attend to the change requests, and I believe that BAE could learn a great deal from reading and responding to those requests. We shall do so in a systematic and organized manner. Challenges Change requests might interfere with our workflow. "Each requested change and recommended action must be processed through the integrated change control process.
The approved changes have their effects on the project management plan, and therefore the plan needs to be updated accordingly," ("Part IV: Monitoring and Controlling the Project," n.d., p. 310). 2. Costs incurred could be significant. The recommended corrective actions, preventive actions, and defect repairs could highlight flaws in our planning. Project Management Solutions 1. Maximize use of information technology designed specifically for our project. We are using a proprietary project management software that was designed specifically for BAE.
I have ascertained that we are under-utilizing this software, especially as we have previously rejected the change requests from the airlines. When we input the airlines' change requests into the software system, those requests will be far less daunting than they appear on the surface. As project manager, I will take full responsibility for the accurate input of the change requests. I will also prepare a full report for management detailing the projected outcomes.
The information technology tools will help the team analyze and control the enterprise environmental factors "that can influence the integrated change control process," ("Part IV: Monitoring and Controlling the Project," n.d., p. 310). 2. Organizational process assets can influence change control processes. This is why I am recommending that instead of rejecting the change requests, that we handle those requests in a systematic manner.
If we continue to ignore the requests and later find out that one of the change requests was for a safety measure that our team had not previously known about, then BAE will be responsible for any adverse outcomes. I strongly advise management to absorb the change requests, and I believe we can handle the input. Our information technology will help us to process the requests. The system will estimate any changes to cost structure. The measurements are also taken care of by the project management system. 3.
Create a formal change request board. We have the personnel to do this, as there are already team members who have volunteered to take this on. "The project.