Paper Example Doctorate 1,098 words

Channel Tunnel and the Seikan

Last reviewed: April 13, 2013 ~6 min read
Abstract

The Seikan Tunnel links Tappi Saki with Fikushima and the Channel Tunnel links the United Kingdom and France. To determine how these projects were engineered, this paper reviews the literature concerning the respective ground conditions at these two tunnel sites, a description of the type of tunnelling techniques that were used and a discussion concerning tunnel displacements and ground movements. Finally, a discussion concerning the reasons for mitigation measures used is followed by a comparison of the two tunnels and a summary of the research and important findings in discussions and conclusions.

¶ … Channel Tunnel and the Seikan Tunnel

Two of the longest tunnels in the world are the Seikan Tunnel linking Tappi Saki with Fikushima and the Channel Tunnel linking the United Kingdom and France. This paper provides a review of the literature to identify respective ground conditions at these two tunnel sites, and a description of the type of tunnelling techniques that were used. A discussion concerning tunnel displacements and ground movements, the reasons for it and any mitigation measures used is followed by a comparison of the two tunnels. A summary of the research and important findings are presented in the paper's discussions and conclusions.

Ground Conditions

Seikan Tunnel. When drilling first started on the Seikan Tunnel in 1961, engineers encountered problems with the unstable volcanic rock under the strait that forced them to resort to less than optimal tunneling methods (Cavendish 2007) which are discussed further below.

Channel Tunnel. The ground conditions on the UK side of the project were deemed generally good enough to allow the use of tunnel boring machines; on the French side, however, engineers were concerned that they would encounter water-bearing fissures that required the use of a more technically complex approach (Harris 2010). In contrast to the tunnel boring machines that were used on the UK side of the Channel Tunnel project, the French approach required the use of tunnel boring machines that could be operated with the workface cutting heads completely sealed in order to create a water-tight operating environment (Harris 2010). These tunnel boring machines were able to "excavate, advance and line a watertight tunnel. In these conditions the tunnel crews need not even see the ground they pass through" (Harris 1996, p. 24).

Tunnelling Technique(s)

Seikan Tunnel. As noted above, the ground conditions and unstable volcanic rock under the strait prevented the use of standard tunnel boring equipment and the construction of the Seikan Tunnel was accomplished through a combination of drilling and blasting (Cavendish 2007). As a result, the tunneling process required a comparatively long time, taking from 1971 to early 1983 for engineers working from both sides to meet in the middle of the strait (Cavendish 2007). Moreover, the first actual test railroad run did not take place until March 1988 (Cavendish 2007).

Channel Tunnel. All told, eleven tunnel boring machine were used to during the excavation (Anderson and Roskow 1999). A narrow-gauge railway was used to keep the supplies moving to the tunnel boring machines as well as to remove spoil from the workface (Anderson and Roskow 1999). In addition, according to Kirkland (2012, p. 48), "Spoil extracted as a slurry via a screw was transported in muck wagons to the bottom of the Sangatte shaft where it was mixed with more water and pumped to the Fond Pignon reservoir."

Tunnel Displacements and Ground Movements (Volume Loss, Monitoring), the reasons for it and any mitigation measures used

Seikan Tunnel. Engineers on the Seikan Tunnel project experienced substantial large water inflows that caused a worsening of the ground conditions (Jha 2012). In response, all tunnel boring machine operations had to be terminated and replaced with the aforementioned drill-and-blast approach (Jha 2012). According to the study of the Seikan Tunnel displacement by Jha (2012, p. 7), "Their flows had to be controlled by grouting which took considerable time, thereby reducing the rate of progress of tunneling. During mid-1981, grout consumption attained 98.2m 3/m and this consumed 67% of the total time. Total drivage amounted to 131m. In 1978 the corresponding values were 5.7m 3/m, 53% and the total tunnel drivage was 1490m."

Channel Tunnel. On the United Kingdom side of the Channel Tunnel project, ground movements were largely restricted to the area that was being worked, with 90mm being measured in an inclinometer that was sited on the toeweight area situated immediately uphill of the toeprint (Kirland 1995). Engineers on the UK side of the project were satisfied of this localized ground movement, though, when these ground movements stopped or quickly stabilized after construction work stopped (Kirkland 1995). By contrast, engineers on the French side of the project were confronted with the presence of faults with comparatively large displacements, as well as a thinner chalk marl that dipped at a more acute angle compared to the United Kingdom side of the project (Kirkland 1995). According to Kirkland (1995, p. 48), "This dictated the choice of closed-face tunnel boring machines that could permit exploratory drilling ahead of the tunnel face as and when required." Generally, no major geological problems were encountered on either side of the Channel Tunnel project, although engineers on the French side of the project experienced inflows fully 20 times as severe as the United Kingdom side (Kirkland 1995). In sum, Kirkland (1995, p. 49) concludes that, "Despite [the constraints encountered], the ground conditions tunneled through were better than those anticipated at the start of the tunnel boring machine drives."

Comparisons

The vastly different ground conditions encountered at the Seikan Tunnel site compared to the conditions encountered by the United Kingdom and the French sides of the Channel Tunnel project dictated the types of tunneling methods that could be used. Although more efficient tunnel boring machines could be used on the Channel Tunnel project, engineers on both sides of this project also encountered sufficiently different ground conditions to require different types of tunnel boring machines. There were some different outcomes concerning the original expectations of engineers concerning what ground conditions they would encounter in the tunnel boring process, with Japanese engineers encountered worse conditions than they expected, and UK and French engineers encountered better conditions than they expected.

You’re 87% through this paper. Sign up to read the full paper.

Sign Up Now — Instant Access Already a member? Log in
130,000+ paper examples AI writing assistant Citation generator Cancel anytime
References
5 sources cited in this paper
  • Anderson, G and Roskrow B 1994, The Channel Tunnel Story, London: E & FN Spon.
  • Cavendish, M 2007, World and Its Peoples: Eastern and Southern Asia, New York: Marshall Cavendish.
  • ‘Ends Meet at World's Longest Hi-Speed Train Tunnel under the Swiss Alps,’ 2010, October 15, Manila Bulletin, 37.
  • Harris, CS 1996, Engineering Geology and the Channel Tunnel. London Thomas Telford Publishing.
  • Kirkland, C 1995, Engineering the Channel Tunnel, New York: CRC Press.
Cite This Paper
PaperDue. (2013). Channel Tunnel and the Seikan. PaperDue. https://www.paperdue.com/essay/channel-tunnel-and-the-seikan-89456

Always verify citation format against your institution’s current style guide requirements.