¶ … project budget of $500,000. The project is a 10-month project and the budget analyst planned to spend $50,000 per month on the project. At month 6, you review the project status and you realize the project is 40% complete. Assume you are at the end of month 6 and will include month 6's work into your EV calculation. The project has spent $425,000 to date. Using the formulas from your book, answer the following questions:
PV = Planned Value is the Scheduled Value = 6 months * $50,000 per month = 300,000
EV = % Complete * Original Budget = 40% * 500,000 = 200,000
AC = Actual Cost of the Work Completed = 425,000 (Given)
SV = EV -- PV = 200,000 -- 300,000 = -100,000
CV = EV -- AC = 200,000 -- 425,000 = -225,000
BAC = Baseline Costs = 500,000 (Given)
EAC = AC + ((BAC -- EV) / CPI) = 425,000 + ((500,000 -- 200,000) / .47) = 1,063,297.83
CPI = Cost Performance Index = EV / AC = 200,000 / 425,000 = .47 = 47%
SPI = Schedule Performance Index = EV / PV = 200,000 / 300,000 = .67 = 67%
Question 2: What does a SPI < 1 indicate?
A schedule performance index that equals a value less than one basically means that the projects schedule is behind its estimated planned baseline. This is evident since the value actually earned is less than the value that was planned to earn at that point in time. If the SPI value is greater than one then that would mean that the project has earned more value at that point in time than it had planned on earning.
Question 3: How does applying earned value calculations help determine project performance in terms of schedule and budget?
Earned value calculation can help gauge a projects performance in a variety of ways. Comparing the earned value to the planned value provides a metric that can help evaluate the project in terms of its scheduling performance. For example, if you planned to earn 80% of the projects value in six months, but you only earned forty percent of that planned value then you would immediately know that you are significantly behind schedule. Determining the cost variance can also utilize the earned value to help provide insights into the project's financial performance. If you projected an earned value that was less than the actual costs then your cost variance would be a negative value and this would represent the fact that the project is under budget for the work performed. These are only a couple examples of how calculations including earned value estimates can serve as a useful metric for any project.
Project Management Although desirable, it is quite difficult to start with a dictionary definition of project management, mainly because of the complexity involved in the process, a complexity impossible to cover with a simple two-line definition. Hence, it is probably best to describe the process, underlining thus the main characteristics of project management. A company's strategic perspective may, perhaps, be amply resumed to two strategic concepts around which everything else revolves: objectives
.....project management approach is increasingly becoming popular in today's workplace. Organisations are ever more recognising the benefits of accomplishing tasks and activities as projects -- better task coordination, quicker task execution, and so on (Larson et al., 2013). The author's organisation, a renewable energy firm with operations in Australia and beyond, has particularly been shifting to the project management approach in recent years. The organisation is currently interested in acquiring
Project Management Plan of a New Restaurant This project management plan is majorly concerned primarily with the first two steps which are defining the project; the project objective is broken down into a series of manageable steps called tasks and designing the project process; this work is performed by the project manager and is presented in the GANTT chart where the tasks are displayed in more detail (Hamilton, 2004). Besides, for
Project Management in a Legal Context Project management is increasingly becoming a popular and preferred way of contending with inter-organizational ventures that are out of the ordinary. When the functions of a project require the involvement of specialized personnel and skill sets which may not be readily represented from within the company to the fullest extent demanded, it may be appropriate to organize a project team. This might be comprised of
Project Management February J. 2014 A project is a temporary group of activity designed to produce unique products and services or results. Typically, a project has a defined beginning and end and therefore having defined scope and resources. (Pierre, 2012). A project also has a specific set of operations to accomplish a singular goal. Examples of projects are as follows: Development of software to improve business process, Construction of bridge or building, Expansion of sales
Project Management Involved Formation of Airbus Project Management involved in Formation of Airbus The report investigates factors that led to the A380 project crisis. Analysis of the project revealed that Airbus did not integrate an effective project management model into the project lifecycle leading the project to be two years behind schedule, which eventually led to the costs escalations. The report reveals several lessons to be learned from the A380 project crisis.
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now