Verified Document

Finance: Evaluating Project Risk The Research Proposal

Instead, we will use the dividend discount model to determine the cost of equity, as follows: D/P (1-F)+g

508/25(1-.15)+.12 = 13.7%

These costs will be constant no matter how much capital is raised. The variable component of the cost of capital is reflected in the flotation costs, which will be a fee at the time of issue. The capital structure is also affected by the amount raised, but there is no indication that a change in the capital structure at this point will result in a change in these component costs. That said, it can be expected that if the capital structure becomes too debt-laden, the company's bond rating could be lowered, and that will increase the cost of debt.

5) the MCC for the intended investments is as follows:

IRR

Weight

Therefore, the five projects in total would have a weighted cost of capital of 17.6%.

6) the Investment Opportunity Schedule shows the following order:

IRR

Cost

Cumulative Cost

If all projects are undertaken, $2.5 million will need to be raised. At this point, all five projects are viable, given that each is above the cost of capital for the firm. The IRR can be increased, however, by dropping the weakest projects. For example, if Project B. is dropped, this will increase the IRR of the remaining four projects to 20%.

The new hurdle rate is the WACC, which is 6.06875%. This gives us new project NPVs as follows:

new NPV

These projects are still acceptable. They still each have positive net present values, which in fact have improved because the cost of...

This assumes that the capital structure of the firm will not change. Even if it assumed that equity will be the source of capital, which would give the project a hurdle rate equivalent to the cost of equity (13.7%), each project still has a positive net present value.
8) if the cash flows from Project B. are more stable than those of the other projects, the best way to reflect this is to adjust the hurdle rate. The hurdle rate is reflective of the project's risk. If we had used CAPM to determine the cost of equity, this adjustment would be straightforward, as we would simply lower the beta by 40% to reflect the lower risk. This is because the beta represents firm specific risk. For most projects, the asset risk is assumed to be the same as the firm risk. If the asset risk is lower, this can be reflected by adjusting the beta.

In this situation, we must adjust the discount rate in another way, by lowering it 40%. This rough estimate will give us a hurdle rate 40% lower, to reflect 40% less risk. This will give B. A different NPV, and that can then be compared directly with the other NPVs.

Sources

Bernard Jacquier the Weighted Average Cost of Capital, 2003. [article online] Accessed August 19, 2008 at http://www.ecofine.com/strategy/wacc.htm no author). The Optimal Capital Budget, no date. [article online] Accessed August 21, 2008 at http://cbe.elmhurst.edu/vcroom/bus441/chapter3.doc

Ben McClure Digging into the Dividend Discount Model, 2008. [article online] Accessed August 21, 2008 at http://www.investopedia.com/articles/fundamental/04/041404.asp

Sources used in this document:
Sources

Bernard Jacquier the Weighted Average Cost of Capital, 2003. [article online] Accessed August 19, 2008 at http://www.ecofine.com/strategy/wacc.htm no author). The Optimal Capital Budget, no date. [article online] Accessed August 21, 2008 at http://cbe.elmhurst.edu/vcroom/bus441/chapter3.doc

Ben McClure Digging into the Dividend Discount Model, 2008. [article online] Accessed August 21, 2008 at http://www.investopedia.com/articles/fundamental/04/041404.asp
Cite this Document:
Copy Bibliography Citation

Related Documents

Kitchen Remodel Project Risk Management You Acquire
Words: 2090 Length: 8 Document Type: Essay

Kitchen Remodel Project Risk Management You acquire knowledge risk management analysis a project. The project remodeling family kitchen. To prepare project, research kitchen remodeling work considerations project success. Hypothesize effect risk management project. Project Risk Management Overall goal of risk management is to guarantee an increase of opportunities and decrease of risk. Risks are uncertain events that occur in the process of project planning and implementation and can have both negative and positive

Project Financing International Project Finance:
Words: 5068 Length: 15 Document Type: Essay

This can subsequently result as the massive benefits to the commercial contestants devoid of the incurring of the extra cost that pertaining to such commercial participants. The participation of the export credit agencies accompanied by the existing multilateral developments institutions normally results to the lofty stage of the ecological, employment and other supplementary social standards, which are extremely expensive and cumbersome to, accomplished. The application these existing social standards are

Finance One Difference Between Industries With High
Words: 1813 Length: 6 Document Type: Multiple Chapters

Finance One difference between industries with high leverage and low leverage is a split between the need for fixed assets (high leverage) and a reliance on intellectual capital (low leverage). Airlines need planes, construction companies need equipment, and communications and hotel companies need infrastructure capacity. This compares with computers, drugs, biological products, educational services and electronics, all of which rely heavily on intellectual property to derive value. The conclusion that one

Finance Ameritrade Is About to
Words: 701 Length: 3 Document Type: Essay

2. The capital asset pricing model can be used to estimate the cost of capital because it allows for an estimate to be drawn as to the company's cost of equity. This can then be plugged into a weighted average cost of capital calculation along with the company's debt and, if relevant, preferred shares. The cost of equity reflects the company's risk in relation to the risk associated with the

Project Management
Words: 3004 Length: 10 Document Type: Essay

.....project management approach is increasingly becoming popular in today's workplace. Organisations are ever more recognising the benefits of accomplishing tasks and activities as projects -- better task coordination, quicker task execution, and so on (Larson et al., 2013). The author's organisation, a renewable energy firm with operations in Australia and beyond, has particularly been shifting to the project management approach in recent years. The organisation is currently interested in acquiring

Risk Analysis Capital Budgeting Risk Analysis in
Words: 1219 Length: 4 Document Type: Essay

Risk Analysis Capital Budgeting Risk Analysis in Capital Budgeting Capital budgeting entails making various decisions in the management of an organization with the aim of determining expenditures on assets. In most cases, these particular expenditures are those that the management expects that their cash flow might extend within a period of about one year. Capital budgeting is a significant process in the management of an organization because it acts a control tool.

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now