¶ … Club Project Initiation
Project Milestone Schedule
Milestone List
Prize Day Club Initiation
Milestone No.
Milestone
Mandatory / Optional
Completion Date
Verification
Project Start
Mandatory
Sponsor Approval
Complete Gathering Requirements
Mandatory
Sponsor Approval
Complete Design
Mandatory
Sponsor Approval
Complete Coding
Mandatory
Sponsor Approval
Complete Testing
Mandatory
Sponsor Approval
Complete Implementation
Mandatory
Sponsor Approval
Project End
Mandatory
Sponsor Approval
Project Budget Estimate
CLUB PROJECT INITIATION
PRIZE DAY CLUB PROJECT INITIATION
Prize Day Club Initiation
Project manager
Sponsor
Budget Status
Approved Budget
Planned Expenditures to Date
Actual Expenditures to Date
Variance
$260,000.00
$260,000.00
$254,700.00
$5,300.00
Planned Remaining Budget
Actual Remaining Budget
Variance
$0,00
$5,300.00
-$5,300.00
Internal Expenses
Salaries
Hourly Rate
# Hours
Total Cost
Project Manager
$35,00
800,00
$28-000,00
Project Supervisor
$25,00
800,00
$20-000,00
Engineering manager
$25,00
800,00
$20-000,00
Design manager
$25,00
800,00
$20-000,00
Financial Manager
$35,00
800,00
$28-000,00
Purchasing
$25,00
800,00
$20-000,00
Other Internal Expenses
Total Cost
Administrative
$5,000.00
Non-administrative
$4,500.00
Book-eeping
$3,200.00
Total Internal Expenses
$148,700.00
External Expenses
Consulting Costs
Total Cost
Design
$12-000,00
Maintenance
$8,500.00
$7,500.00
Capital Expenditures
Total Cost
Building
$35-000,00
Electrical
$18-000,00
Furniture
$25-000,00
Total External Expenses
$106,000.00
Total Budget
$254,700.00
Assumptions, Constraints and Risks
The project assumes that human and financial resources estimated for the project will be available and sufficient for the project. It is assumed that the time frame allotted for the project is sufficient to complete the project. Moreover, it is assumed that all the materials and equipment will be available to complete the project with no unreasonable delay. It is also assumed that inflation may increase the costs of materials, which may escalate proposed budget. However, the project sponsor has not approved the budget and this need to done before the project starts. Non-availability of the key resources may affect project completion at the time schedule. (Project Management Institute, 2013).
Communication Plan
Project Management: Procurement Management Plan Procurements Management All aspects of the procurement management plan will be handled in accordance to the communications matrix, and the various methods for communicating indicated in the Communications Methods and Technologies section of the Unit 1 X Price Day Club Project Initiation. As it pertains to Procurement Management aspect, the Project Management Book of Knowledge outlines a four step process for ensuring proper facilitation of the procurement
Market Orientation of Medical Diagnostic Units Dissertation for Master of Health Administration i. Introduction ii. Objectives iii. Description iv Administrative Internship v. Scope and Approach vi. Growth vii. Methodology viii. Hypothesis ix. Survey Questionnaire x. Research Design xi. Observation and Data Presentation xii. Test provided xiii. Analysis of findings Marketability of Patient Satisfaction Importance of Employee Satisfaction xiv. Conclusions and Recommendations xv. Bibliography xvi. Notes xvii. Appendices Market Orientation of Medical Diagnostic Units
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now