Project Management For Greendale Baseball

Greendale Baseball Stadium Case Study Assessment whether the project be completed by May

The entire calculation reveals that the project's life cycle will take a total of 695 days to complete, which will end on February 27th, 2014. Based on the projected trajectory, the project will be completed 54 days ahead of the project schedule making the project manager to complete the project before May 20, 2014, the project deadline. However, the project is not without its challenges because the entire project duration is 1,695 days, which is far more than the project estimated life cycle. To address this problem, the project stakeholders will implement many of the project tasks simultaneously. For example, the project will be divided into three phases: Phase I, Phase II, and Phase III. The tasks and timeframes of these phases will be run concurrently to meet the due date. Moreover, the work packages in the three phases will be codependent with one another to achieve the project success.

Table 1: Project Phases

Phase I

Phase II

Phase III

Clearing project site

Building demolition

Building the support site

Driving the support pilings

Concrete bowl construction

Main concourse construction

Playing field install

Upper steel bowl construction

Installation of Seat installation

Installation of Luxury box

Installation of Jumbo Tron i

Stadium infrastructure (locker rooms, bathrooms, restaurants, etc.)

Construction of Steel canopy

Lighting Installation

Retractable roof installation

Planning of retractable roof and construction will run concurrently and parallel to the entire project. (This task represents the critical path)

Stadium Inspection

Estimated Tasks Completion: 460 days

Estimated Tasks Completion: 240 days

Estimated Tasks Completion: 305 days

Critical Path for the Project

The following are important to take into a consideration when developing a critical path for the project: First, a list of activities required to complete the project should be within the WBS (work breakdown structure). There is a need to calculate the time duration of each activity.

There is also a need to identify any dependencies between the project activities.

As being revealed in Table 1 and Fig 1, the tasks in the phase III represents the critical tasks showing that planning of retractable roof and construction of steel canopy will run concurrently and parallel to the entire project.

Fig 1: Project Tasks and Time Frame

Slack / float...

...

Stated in different words, the total slack refers to the activities that will exceed the project finish date without affecting project due date. Typically, the total slack is the difference between LF and EF (LF ? EF = SL) or different between LS and ES (LS ? ES = SL). The free slack in the project is 481 days and the activities having the greatest slack is "set up the construction site" as being revealed in Fig 2.
Fig 2: Slack or Float in the Project

Top three Activities that could impact the Project Due Date

The study carries out the project risk assessment to identify the activities that may have the greatest impact on the project. As being revealed in Table 2, material delay, weather related delay, and roof install delay are the activities that can have the greatest impact on the entire project.

Table 2: Project Risk Assessment

Risk Event

Likelihood

Impact

Detection Difficulty

When

Weather related delays

3

3

4

Entire project

Materials delay that includes Shipping, etc.

2

3

5

Entire project

Roof install delay

2

4

4

Phase III

Installation delays (manpower, materials)

2

4

3

Entire Project

Phase delays

3

3

3

Phase II, & III

Overall project delay

2

4

5

Entire Project

Potential to crossover to scheduled end

2

5

4

Phase III

Additional activities adding to the Project

The study presents the contingency plan to reduce the impact of the risks using the risk assessment matrix in table 3. The strategy assists the management to manage the impact of the risks that could affect the project lifecycle.

Table 3: Contingency Plan

Risk Event

Response

Contingency Plan

Trigger

Who Is Responsible

Weather related delays

Reduce

Implement 24-hour shifts or work extra hours to make up a lost time

Project is pushed back by more than 48 hours within any phase

Project manager and Phase manager

Materials delay

Reduce

Locate eventual source for the new materials

In all areas project…

Cite this Document:

"Project Management For Greendale Baseball" (2016, July 27) Retrieved April 27, 2024, from
https://www.paperdue.com/essay/project-management-for-greendale-baseball-2161114

"Project Management For Greendale Baseball" 27 July 2016. Web.27 April. 2024. <
https://www.paperdue.com/essay/project-management-for-greendale-baseball-2161114>

"Project Management For Greendale Baseball", 27 July 2016, Accessed.27 April. 2024,
https://www.paperdue.com/essay/project-management-for-greendale-baseball-2161114

Related Documents

Baseball and the American Character The three essays on baseball, by Allen Guttman, Murray Ross and Michael Mandelbaum, are all well written and supply unique opinions and ideas about baseball and America that are interesting but quite different. In this paper the writer will take a position on the debate that is going on with these three writers. Allen Guttman's Essay Guttmann reviews the phases of the American experience to explain what is

Baseball in 1860 -- 1900:
PAGES 5 WORDS 1520

With a less stronger structure and with the fact that it had no history whatsoever, baseball did not appear to be the next big thing in nineteenth century Canada. Surprisingly, however, the sport grew into the hearts of the Canadians and quickly replaced cricket and lacrosse. Even though the game is played at a different level in Canada, the Canadian teams have been reported to be worthy of competing

Baseball is a sporting game, whereby only a baseball bat, baseball glove and a ball are used, it is played between two teams, one is called the batting team and the other is the fielding team each consisting of nine players. Goals are awarded depending on the numbers of runs, of which to complete one run a player has to hit a ball thrown at him and then touchdown on

The age of the stadium can be appealing if the stadium is rich with history, or if it is new and equipped with the most modern features. However, middle-aged stadiums may have neither appeal and could result in depressed attendance figures. The number of wins that the team has in the season impacts fan interest, as does the team's salary (which is a good way to operationalize a team's

As a young pitcher, I had pretty good mechanics thanks to my father's coaching. His influence on my style did not always please the high school coaches but it did not take them long to notice that whatever I was doing worked. Yet I also had to work hard at surrendering my pride. I needed to incorporate the coaches' wisdom with that of my father's and blend it all

What I also find fascinating about early baseball is how early baseball evolved into the business it is today. Expansion of teams into new markets first occurred in the 1960s ("The History of Baseball" nd). Players, fans, managers, and team owners as well as cities started to view the sport more as a business opportunity than simply a pastime. Before long, the players formed a labor union and their high