How does resource scheduling tie to project priority?
The purpose of the project priority system is to select projects that are in line with the plan and objectives of the organization. In order to select these projects, the project manager must know what resources are available to work with.
Present six reasons scheduling resources is an important task.
Resource scheduling before the start of the project can avoid the following pitfalls:
Resource deficiency at particular intervals of the project.
Increased project duration.
Shift of technical constraints.
Higher project costs.
Non-effective use of available resources.
Inability to secure necessary outside contracted help.
Explain the risks associated with leveling resources, compressing or crashing projects, and imposed durations or "catch-up" as the project is being implemented.
Leveling resources lowers the flexibility within the project. Using this method requires the project manager to decrease the number of activities so that only the critical" activities are implemented. This slack reduction could instead create more activities, which could extend the project duration.
Like leveling resources, the purpose of compressing or crashing projects and catch-up is to hasten or do away with activities so the project is completed sooner than predicted. This narrowed focus on key activities could promote the development of a new path, which could lead to higher project costs.
Imposed duration, although known as a low-cost method, could, due to its nature, cause more mistakes, which could potentially add to the project time and increase cost.