Project Management Scenario A Global Case Study

" The rule to adopt to schedule the project is to efficiently allocate the resources to achieve early start schedule. Given the limited resource, the constraint to be taken into account is the resource requirement, which is required to avoid extreme fluctuation in the labor demand. The resources constraints could lead to high costs of labor training, transportation, hiring and management. Additional constraint is that there is much difficult in presenting the project network diagram, and too much information is often presented which could be high as 500 activities. The problem of displaying numerous activities is identification of activities such as number resources to be added to the diagram.

Q7). a) "Find the expected time of the project using PERT. What is the probability of completion within the expected time"?

The expected time of the project using PERT is calculated using weighted average and the results gives Time Expected (Te).

a m m

Te

A

2

4

6

4

B

4

6

8

6

C

2

3

4

3

D

0.5

1

4

1.83

E

2

3

4

3

F

1

3

5

3

G

1

2

3

1

H

2

3

4

3

I

1

2

3

2

J

0.5

1

3

1.5

K

0.5

1

3

1.5

L

1

3

5

3

The probability of completing the project within the expected time is as follows:

4+6+3+1.83+3+3+1+3+2+1.5+1.5+3/12

32.83/12=2.73

The probability of completing the expected project before the expected time is

1.46 which is greater than 1. When using probability analysis, the care than needs to be taken care of order of magnitude.

Q8). "Find the minimum cost increase to reduce the expected duration of the project by 2

Weeks."

Activity

Minimum Cost

Normal Duration

Crash Cost

Crash Duration

Change in Cost per Day

A

B

C

D

E

F

G

8

4

8

10

10

20

10

6

1

8

5

9

12

3

14

4

24

24

18

36

18

4

1

4

3

5

6

2

3

4

7

2

2.7

8

Q9). "The Company assessed the costs of the project at important milestones at the outset as shown in Table B2. After some weeks, the project manager asked the task supervisors for progress reports and the feedback shown in Table B2 was reported."

a) What is the cost variance...

...

The project is ahead of schedule and over budget.
b)

y+2x = 7.45

y-x =1.75

y=1.75+x

1.75+X+2x = 7.45

1.75+3X=7.45

3X=7.45+1.75=5.70

X=1.90

y-1.90 =1.75

Y= -0.15

X=1.90X900= 1710

Y=-60

The minimum cost is 1710-(-60)

=1710+60=1770/2

Minimum cost=£885

Minimum cost corresponding to the optimal values of the decision variables is £885.

Sources Used in Documents:

References

Anbari, F.T., Carayannis, E.G. And Voetsch, R.J. (2008) Post-project reviews as a key project management competence, Technovation, Vol. 28, pp.633-643.

Brady, T. And Davies, a. (2004) Building of the Project Capabilities: From Exploratory to Exploitative Learning, Organization Studies, Vol.25, No.9, pp.1601-1621.

Prencipe, a. & Tell, F. (2001). Processes and outcomes Inter-project learning: knowledge codification in project-based firms. Research Policy. 30: 1373 -- 1394

Plan:


Cite this Document:

"Project Management Scenario A Global" (2012, March 03) Retrieved April 16, 2024, from
https://www.paperdue.com/essay/project-management-scenario-a-global-54720

"Project Management Scenario A Global" 03 March 2012. Web.16 April. 2024. <
https://www.paperdue.com/essay/project-management-scenario-a-global-54720>

"Project Management Scenario A Global", 03 March 2012, Accessed.16 April. 2024,
https://www.paperdue.com/essay/project-management-scenario-a-global-54720

Related Documents

(Braunschweig; Day, 150) Most of the current generation of project managers expects the project management tools to furnish them with almost real-time knowledge in order to facilitate their decision-making. Some of these tools like DOFF, "Field of the Future," "Smart Fields," Microsoft's "Oilfield Connectivity" and i-Fields are currently being examined by exploration and production oil companies. Some of these tools have the capability of generating information from apparently incongruent data

Project Management In order to define project management, one must first define what is a project. A project is a temporary activity performed by a group in order to develop a unique service, product, or result. A project is labeled a temporary activity because it has a defined start and end in time. Therefore, a project has a defined scope and resources. This means that a project can only be carried

Project Management: Case Study in Managing a Complex Shipyard Project in Singapore Background of Complex Shipyard Construction Project Company background Project Overview and Objective Work Process of Building Construction Issue Analysis in Shipyard Construction Project Management Literature Review of Project Management Issues in Scope Management Methodology of Scope Management Lessons Learned from Scope Management Issues in Cost Management Methodology of Cost Management Lessons Learned from Cost Management Issues in Human Resources Methodology of HR Management Lessons Learned from Human Resource Management Case Study in Managing a

(Chaffey et al., 2006) The enhanced version of the website will be designed in such a way that it gets integrated into the existing systems by reading and saving data to those systems. This website will also maintain a log for the management to review the nature and reactions of traffic on the website. In order to attract more traffic, user will be given the opportunity to view results as

Project management is a systematic methodology of attaining aims and objectives in a given criteria for instance time and budget spread on number of years. Project management has been behind every major project for instance man landing on the moon to polio campaigns throughout a country (Gray CR and Larson, 2008). The subject of project management has grown and blossomed over a number of years. It dates back to cavemen. The

It has been widely accepted as an industry standard for project management software. Many large companies such as Intel have benefited from it to the extent that case studies were conducted on the results. Many such case studies are documented on Microsoft's website as a testament to the success of this utility. Microsoft Project allows employees, resources, and tasks to be defined. A wide range of relationships can be