Capital Budgeting If the discount rate is 0%, the project's NPV is $670,000. If the discount rate is 2%, the project's NPV is $614,353.50. If the discount rate is 6%, the project's NPV is $514,815.60. If the discount rate is 11%, the project's NPV is $408,997.50. The project's modified internal rate of return is 39%. The chart will show that the net present value is zero will at 46%, as this is where the NPV intersects the y axis. This implies that when the discount rate is 28%, the project will have a zero NPV. This number should be equal to the internal rate of return, but of course the modified internal rate of return (MIRR) and the internal rate of return (IRR) are different numbers, because of the impacts of compounding.

For the second equation, if the discount rate...

...

If the discount rate is 4%, then the NPV of the project is $7,593.31. If the discount rate is 10%, the NPV will be -$91,776.90. If the discount rate is 18%, then NPV will be -$197,892. The MIRR for the project will be 3%. When the line is drawn, the NPV intersects with the y-axis at around 4.5%. This means that at around that point, the project's NPV will be zero. If the discount rate is higher, the project should not be undertaken. If the discount rate is lower, the project can at that point be undertaken.
To determine the NPV of this project, multiply the initial investment by the profitability index. In this case, .2 * 0.94 = $188,000. This means that while the project pays back the initial investment, it does not do so…

Cite this Document:

"Capital Budgeting If The Discount Rate Is" (2011, July 04) Retrieved April 19, 2024, from
https://www.paperdue.com/essay/capital-budgeting-if-the-discount-rate-is-51393

"Capital Budgeting If The Discount Rate Is" 04 July 2011. Web.19 April. 2024. <
https://www.paperdue.com/essay/capital-budgeting-if-the-discount-rate-is-51393>

"Capital Budgeting If The Discount Rate Is", 04 July 2011, Accessed.19 April. 2024,
https://www.paperdue.com/essay/capital-budgeting-if-the-discount-rate-is-51393

Related Documents

Capital Budgeting for Guillermo Furniture Guillermo Navallez, owner of the relatively small yet highly successful furniture manufacturer Guillermo Furniture, is faced with a tough decision. Due to changes in the industry an in his operating atmosphere, Guillermo is unable to continue competitively running his company as he has for the past decades, with a crew of skilled laborers building furniture and with distribution handled essentially by the company itself. He must

Generally speaking, the higher a project's internal rate of return, the more desirable it is to undertake the project. As such, IRR can be used to rank several prospective projects a firm is considering. Assuming all other factors are equal among the various projects, the project with the highest IRR would probably be considered the best and undertaken first." The equation to calculating the internal rate of return is a

Capital Budgeting is a vital part of any business. Investment decisions, which need time to mature, must be based on the returns that they will make. If investment in a project is unprofitable in the long run, it would be unwise to invest in it. However, if the investment will be profitable, it is important to determine this early in the game. Because huge sums of money can be lost if

Any discount rate lower will yield a positive net present value, up to $126,000. Part II. For capital budgeting decisions, NPV is a better metric. NPV and IRR are very similar in many respects, and they carry the same reliance on the same underlying assumptions about the underlying cash flows. Additionally, they both relate to the company's cost of capital. IRR is typically used as a go/no-go threshold, whereas NPV measures

When a range of options are presented to management, the capital budgeting process must be used to determine the costs and cash flows associated with each option. However, the capital budgeting process is only as valuable as the inputs and assumptions. If the assumptions are not grounded in reasonable analysis and quality research, the process will not yield a valuable result. If the numbers that are input into the

For company B, the risks associated with cash flows are higher than that for company A, and are in the order of 11%, but nevertheless, the IRR on the cash flows is higher than the minimum required rate of return of 11% making this investment also attractive. As these two projects are mutually exclusive, and considering only IRR investment selection criteria, purchase of company B. with IRR of 14,305%