Appellate Opinion In The Case Research Paper

PAGES
12
WORDS
3783
Cite

7). This point brings up one of the larger issues suggested by the opinion (which will be discussed in greater detail later), namely, the fact that the conflict between the law's position on jurisdiction and this kind of estoppel is "yet another case where the government has 'taken entirely irreconcilable positions regarding the jurisdiction of the federal courts," leading to increased litigation and cost (Lettow, 2012, p. 7). Thus, though he is reluctant, Lettow agreed that "draconian as it may be, this court nonetheless is compelled by law to ignore the government's prior acceptance of jurisdiction in the district court" (Lettow, 2012, p.7). Though this will be addressed in greater detail later, the problematic nature of this legal obligation is the fact that the time spent litigating the case in the district court, when Union Pacific believed that court to have jurisdiction, contributed to the expiration of the statue of limitations, suggesting that plaintiffs with legitimate claims may ultimately fail in litigation solely due to a kind of confusion on the part of the courts. Normally the accrual begins at the time of the breach, but Union Pacific was able to make a convincing case that neither the Katy nor Union Pacific could have been aware of the Corps' installation of the incorrect culverts at the time or subsequently. Judge Lettow ultimately decided that accrual did not begin at the time of the breach, but rather when it was discovered, because even though the contract required the Katy to "make a detailed inspection' to determine whether 'the completed sector of the railroad [was] constructed in accordance with the approved plans and specifications,'" the fact that there was no water in the adjacent reservoir would have made it difficult if not impossible for an inspector to determine on sight that the culverts were below the eventual water line (Lettow, 2012, p. 8). Furthermore, Lettow decided that the accrual should not have begun at the time of the derailment, because even though an investigator could have seen that the culverts were made of metal instead of concrete, investigators may not have been aware of the details of the contract at that time.

Union Pacific attempted to further argue that the date of accrual should begin in February 2007, when it first received the Corps' "as-built" drawings which demonstrated that it had in fact installed metal culverts without the consent of a Katy engineer, but Lettow denied this date, deciding instead that the accrual began in May 2005, when Union Pacific first filed its administrative claim with the Corps. Because Union Pacific acknowledged the metal culverts as both the cause of the derailment and a breach of contract in that administrative claim, there was no choice but to determine that Union Pacific was aware a breach occurred, and thus accrual must begin. As a result, Lettow had no choice but to dismiss the claim, given that the statue of limitations had expired by the time Union Pacific brought the case to the Court of Federal Claims in February 2012.

Perhaps the most obvious issue raised by this decision is the aforementioned "draconian" necessity of enforcing a statute of limitations such that a case is dismissed even as the plaintiff, acting in good faith, specifically did not take the case to the Court of Federal Claims out of a belief that the district court had jurisdiction over the matter. From an outside observer, this would seem to grant an unfair advantage to the government, who, as in this case, can acquiesce to a district court's jurisdiction simply as a means of "running out the clock" until the applicable statute of limitations expires. The problem is not that claims can expire, but rather that the particular process of the courts, and particularly the Court of Federal Claims, may be set up in such a way as to give the government unwarranted advantage in defending itself from legitimate claims.

That the government attempts to exploit jurisdictional issues in its cases before the Court of Federal Claims is not in question, as evidenced by two recent opinions issued by that same court, Extreme Coatings Inc. v. The United States and Hartford Fire Insurance Company v. The United States. In the former case the government attempted to have the case dismissed on the grounds that the plaintiff did not properly file a claim to the government contracting officer, and as such the court did not have subject matter jurisdiction over the claim (Wheeler, 2012, p. 1-2). In that case the judge denied the government's motion and stayed the case for thirty days to allows for the claim to be...

...

This is not to begrudge the government its right to question jurisdiction in its own defense, but simply to point out that it is a common and (although not in the case of Extreme Coatings Inc.) useful tool.
The other decision, Hartford Fire Insurance Company v. The United States, did not rest entirely on issues if jurisdiction, but questioning jurisdiction was a central component of the government's defense that the plaintiff had failed to make a claim that could be compensated. At issue was a contract between the Hartford Fire Insurance Company and the Army Corps of Engineers, and in particular whether or not the Corps had wrongly disbursed funds to another contractor with whom Hartford was associated. In that case, the government argued (among other things) that "any lawsuit Hartford might have would be more akin to an impairment of suretyship claim, which cannot be maintained against the United States" (Futey, 2012, p. 5). The judge ultimately denied the government's motion, finding both that Hartford successfully stated its claim and that the court itself had jurisdiction over the case.

Both opinions further demonstrate the importance of the Court of Federal Claims to contract law, because the Tucker Act makes the Court the preeminent authority on large government contracts, which have rapidly become one of the most lucrative kinds of employment for large firms. Anytime something happens with these (sometimes multibillion dollar) contracts, the Court of Federal Claims hears the case, such as "a multibillion dollar government contracts claim regarding the B-2 stealth bomber [and] a multibillion dollar claim and $111 million award to Hughes Aircraft for unauthorized government use of its satellite guidance technology" (Carter, 1997, p. 75). More recently the court decided in a multimillion dollar suit between Daewoo Engineering and Construction and the government, deciding that Daewoo had submitted false claims and was responsible for over seven million dollars in damages after failing to complete a road in the Republic of Palau (Rosetti & McKeeman, 2007, p. 13). Thus, the Court of Federal Claims plays an outsized role in the economy at large, because it is responsible for hearing claims from the world's largest companies, many of whom got that way via government contracts. As a result, problems or complications with federal contract law can have far-reaching ramifications, not only for the companies involved, but also for the public at large, who frequently deals with these companies or their handiwork without their knowledge.

The issue of the Court of Federal Claims' jurisdiction is a serious one, because relatively recent Supreme Court decisions have served to gradually erode that jurisdiction, such that in some cases "two plaintiffs with substantively identical claims may thus end up in different courts, merely because the form of their pleadings differ" (Thies, 2010, p. 1203). For example, in its 1988 decision in Bowen v. Massachusetts, the Supreme Court decided that district courts could hear contract cases against the government "so long as the pleadings characterized the claim as seeking 'declaratory or injunctive relief' rather than 'money damages,'" (Thies, 2010, p. 1203). The problem with this complication of jurisdiction is that it opens up plaintiffs and defendants alike to the kind of jurisdictional and statute of limitations issues that arise when cases are bounced from one court to another independent of the regular appeals process. As Lettow lamented in his opinion, and other commentators have expressed elsewhere, the "costly and time-consuming path through federal District and appellate courts" frequently serves to derail the course of justice by using the letter of the law to contradict the spirit of it ("Taking on takings law," 1997, p. 74).

Considering the sheer monetary value of the cases considered by the Court of Federal Claims, the public policy implications of the Union Pacific Railroad decision should be staggering. Although this particular case only concerned roughly $4.5 million, which is not very large in the world of government contracts, the fact that its conclusion ultimately rested on the government being able to run out the statue of limitations by initially agreeing to the jurisdiction of the Oklahoma district court should give legislators and the public pause, because this suggests that the law governing federal contracts is contributing to serious inefficiency and waste, both in terms of litigation and contracting. There are entire industries…

Sources Used in Documents:

References

Anonymous. Taking on takings law. (1997). ABA Journal, 83, 74.

Carter, T. (1997). The court conjurer. ABA Journal, 83, 72-75.

Futey, B. (2012). Hartford fire insurance company v. The United States. United States Court of Federal Claims.

Kahan, M., & Edward, B.R. (2011). When the government is the controlling shareholder. Texas Law Review, 89(6), 1293-1364.


Cite this Document:

"Appellate Opinion In The Case" (2012, October 31) Retrieved April 25, 2024, from
https://www.paperdue.com/essay/appellate-opinion-in-the-case-76238

"Appellate Opinion In The Case" 31 October 2012. Web.25 April. 2024. <
https://www.paperdue.com/essay/appellate-opinion-in-the-case-76238>

"Appellate Opinion In The Case", 31 October 2012, Accessed.25 April. 2024,
https://www.paperdue.com/essay/appellate-opinion-in-the-case-76238

Related Documents

Appellate Court Case Opinion Breach of Contract The appellate course opinion (state) that will be analyzed in this text is that of John E. Brock (Plaintiff) v. Johnson Breeders, Inc. (Defendant). This was selected owing to the lessons it presents in relation to repudiation of a contract. The case selected is in line with the course’s objective of further enhancing understanding of not only the creation, but also the management as

An appellate court case that found the employer liable for hostile environment sexual harassment is Kunin v. Sears Roebuck & Co. Under this claim, Karen Kunin was sexually harassed by a male employee based upon the abusive and derogatory language that was used. Kunin did not report any abuse to her employer other than to asking if cursing was harassment. The U.S. Court of Appeals found that an employer must

Harassment Case Sexual Harassment at Teddy's Supplies: Case Analysis Teddy's Supplies' CEO has asked you to advise him on the facts of the case and your opinion of their potential liability. Write a memo to him that states your view of whether the company is exposed to liability on all issues you feel are in play. Include in your memo any laws that apply and any precedent cases either for or against

Gault Caption: In re Gault et al., 387 U.S. 1; 87 S. Ct. 1428; 18 L. Ed. 2D 527; 1967 U.S. LEXIS 1478; 40 Ohio Op. 2D 378. Facts: After allegedly making obscene phone calls to a neighbor, the appellants' son, a fifteen-year-old boy, was taken into custody by the Gila County sheriff. The detention occurred without notice to the parents. The boy was questioned without being advised of his right

Reasonable Suspicion and 4th Amendment Law in U.S. v. Arvizu, 534 U.S. 266 (2001) Title and Citation: U.S. v. Arvizu, 534 U.S. 266 (2001) Type of Action: Review by the U.S. Supreme Court of a ruling made by the U.S. Court of Appeals for the Ninth Circuit, which held that evidence should be suppressed as a result of a violation of the Fourth Amendment right to privacy and protection from unwarranted and

Appellate Case in Which a
PAGES 2 WORDS 653

It would be like selling a car for ten bucks one year and then demanding and getting a new agreement the next year for the same car even though ownership has already been transferred. The agreement in 1991, in the opinion of the author of this paper, was basically window dressing for what had already occurred the year prior. As such, it is not enforceable. Final Opinion It surely seems the