This paper looks at a group of questions that were asked with regard to the text readings and different case scenarios offered in a project management text. The questions cover balanced planning, project selection, a case study about a project that had gone wrong, and others that have to do with the basics of IT project planning. All questions were answered in about 2 pages (600 words) for each.
¶ … trouble with Philadelphia's water billing system is a technical problem or a people problem? Why?
From the case study it is at first difficult to separate the two and decide whether the issue rests mainly with the people involved or the system. The people who developed the system did not anticipate using it for such a broad application, so they are responsible for not preparing the system for such an application before they tried to use it. The system itself cannot handle the complex load required of a water billing system to the 500,000 customers that reside in Philadelphia. In the end, it seems more likely that this was "operator error" more than something that was wrong with the system itself. This will become apparent in the following discussion.
The first group of people who made an error were the city officials who did not conduct an adequate amount of research before they selected a plan. Oracle is known to have reliable IT solutions, but it would have been simple for the people in charge of acquiring the needed system to look at the company's track record. Oracle was made for projects that are much smaller in scale, and this could have been very easily determined. Because the city managers did not initially do their homework, they are largely responsible for the delays and cost overruns that have occurred.
The people at Oracle may be even more responsible. They knew what their system would do, and they still decided that they could take on a project that was beyond their capabilities. It would have been better if they had developed the needed system before they decided to take on a job that was too complicated for what they could offer. The case study relates that the Oracle systems had worked well in the past for other projects that they had taken on, but these projects were not close to the scale of the Philadelphia project. Trying to work on the fly to correct the flaws in the system as applied to this much larger project has obviously meant that there have been delays.
On the other hand, Oracle has said that they have met what the agreement spelled out, so this is, again more of a city manager issue. The city managers should have known the scope of the project, and been able to tell what type of system they needed while they were searching. It seems, from the case study, that the water department knew that the system was not sufficient to conduct billing operations for the city, and this should have been heeded by the mayor's council and other decision makers.
It does not seem that there was an adequate plan in place when the project was begun. Apparently the goal was known, but alternatives to reach that goal were not researched carefully enough. The stakeholders involved in the initial planning of the project should have paid more attention to what the final goal was. There was also a need to use some of the techniques discussed throughout the text to ensure that the project went well. This case is a demonstration of what happens when the planning phase of the project is not given enough gravity. Apparently, the city managers believed that they would get the best possible product from Oracle without doing much planning, and Oracle too on the project without examining their software to the needed extent. Because the people did not don their jobs, the software aspect was doomed from the start.
2. a. Discuss the criteria that should be used to make a project selection decision.
The decision whether or not to take on a particular project is often not an issue because there are no competing projects that interfere with each other. However, sometimes time is of the essence and a manager must decide between several seemingly worthy projects. According to the text, the method used to make such a decision is called the "balanced approach." It is balanced because it uses four selection criteria that are not weighted, but given equal importance when choosing the project. The four criteria are finance, customer satisfaction, internal business processes, and the organization's ability to innovate and learn (60). These criteria take into consideration all of possible aspects of any given project that are important to a company.
This four-pronged approach provides a much more reliable baseline than traditional financial planning alone can provide. The text says that traditional financial measures have been likened to "steering the boat by watching the wake" (61). It is important to consider the financial aspects of any plan because stakeholders will expect fiscal responsibility, but this cannot be the only criteria. Customer satisfaction plays into the plan because it is the customer who is the most important stakeholder to the business. If the goal is to make money, as it usually is in business, then the people who supply the money by purchasing products or services are more important than anything else. The processes tie the financial and customer perspectives together for the most part. The processes that the company uses must be maximized so that financial and customer satisfaction goals are reached. Finally, if a company is not learning from its current and past processes, then it is not moving forward. The balanced plan has to allow the company to progress toward its larger goals.
b. What is a baseline plan? What purpose does it serve once the project team begins to execute the project plan?
The text, on page 18, defines a baseline plan as that which "defines the projects scope, schedule and budget and is used as a tool to gauge the project's performance throughout the lifecycle." This is the initial plan during which the foundational questions are asked and answered. With this plan, the project manager(s) has the ability to construct the more detailed elements of the project.
This plan is used throughout the project to make sure that every aspect of the project is on time and being completed to the agreed upon specifications. It is "reviewed by the project manager, project sponsor and the project team" to make sure that everyone understands what is required of both the team and the what the end product of their endeavors will be. On page 93 of the text it says that "once the project plan is approved, it becomes the baseline plan which will serve as a benchmark to measure and gauge the project's progress." However, it is just a guide, and it can be changed as more information becomes available.
One of the primary purposes of the plan besides that of benchmark is to keep the project on track. "The project manager will use the baseline plan to compare the actual schedule to the estimated schedule and the actual costs to the budgeted costs." The reason that the project manager keeps a close eye on the plan is because this is the plan that was agreed to by all stakeholders in the project. If it becomes necessary to change elements of the plan because of unforeseen difficulties, then it is the project manager who should have a clear grasp of what was expected and what the new expectation will be. He or she must be able to communicate this effectively to the project sponsor, so that if more money or time is needed the project manager can go directly to the plan and show the steps that will need to be changed and why.
3. 1. Create a list of project stakeholders.
The primary stakeholder for this project is Scully because it is his company, and because he is the power behind Husky and because he controls the finances. He needs to look at all aspects of the project as he is the project sponsor and work with the project manager to set the baseline plan for the project. He is also responsible for easing or moving a few potential roadblocks. Since he is the CEO he is able to let employees go of they are no longer able to perform their duties up to the changing standards of the company. However, he should not be quick to remove employees because there may be repercussions if he removes the wrong employee without giving her time to acclimate to the new standard.
Alma has said that she will retire if she has to learn a new, complicate system. But, she has always kept the record for the flights, and she is the one indispensable link in this chain. She knows the pilots and they respect her; she knows and has connections with suppliers of needed goods; and she has been a valuable employee for many years. Her present stubbornness notwithstanding, Alma is essential to the success of this program. She also needs to be flexible because this is a humanitarian effort which is more important than her fear of technology.
The project manager, Tim, has a need to see this project work successfully, but he has to define carefully what success entails. Since Alma is an important cog, he must accommodate her wishes. The project manager would be wise to make sure that this project will meet the needs of the company, but also be completed so that all of the stakeholders can be accommodated to the best of his ability. The success of the project is not just determined in it completion, it is determined in ease of operation, monetary savings, and the ability of the humanitarian effort to continue to move along smoothly.
The three techs -- Sitaramin, Yan and Pat -- are responsible for making the system as friendly as possible. But, they also cannot be influenced too much by Alma. She wants a system that is so simple that it takes no time to learn and with which she can smoothly transition from the old to the new. Unfortunately, this is rarely possible. The techs need to make sure that the system is user friendly, but also that it performs the need functions.
The volunteer pilots need to understand where they are going, where they are going to get fuel, and what their individual schedules are. The new system has to be able to tell them all that they need to know in order to operate without any hitches. They may also be valuable assets in helping Alma get over her fear of technology.
The passengers are, in the end, the most important entity, and they need to be accommodated by all of the other stakeholders. As consumers, they are the reason for the humanitarian mission, and a better scheduling plan should ultimately benefit them more than Alma's current system. They are the ones everybody needs to be thinking of as the new system is designed.
2. Complete the Analysis
Stakeholder
Interest
Influence
Potential Conflicts
Role
Objective
Strategy
L.T. Scully
+1
5
None
Leader
Go Between
Ease Tensions
Alma Coleman
-1
4
Does not like the idea of a new computer system
Naysayer
System Expert
Accommodate
Tim Williams
+1
2
Alma and Pilots
Project Champion
Project Manager
Be Flexible
Sitaramin, Yan and Pat
+1
2
Alma
The Glue
New System Experts
Marry the two systems
Volunteer Pilots
+1
2
Tim
Possible Allies
Positive Input
Learn the new system
Passengers
0
0
none
Consumers
Consumers
Consumers
4. 1. Why should the government consider developing a business case for antiterrorist data mining projects?
The short answer is yes they should, and for some very good reasons. The problem with too many government agencies is that they seem to regard the money they receive as their own. Congress budget sends a certain percentage of the overall to different departments and the split can be quite large. Because the budgets of some agencies, especially homeland security, continue to grow, there seems to be no oversight as to where the money is going. This can be seen in the test case when a former CIO is talking about how the data mining projects he witnessed seemed to have no real efficacy. Of course, the fact that the money is not their own is a secondary consideration to another issue. This use of random data mining can be seen as a violation of American civil liberties, and it is very likely that people will sue which will in turn tie up more government resources and tax payer money. The data from these projects, since it is random and seems to have little purpose, is questionable. It may be difficult for the data obtained to even generate warrants.