El-Gafy (2008) argues that risk analysis is needed in order to determine the potential impact of risks. Both qualitative and quantitative techniques are used for the risk analysis, however, qualitative approach consumes more information and there is a need to gather large amount of information compared to the quantitative approach that require lesser information. Typically, the quantitative risk analysis approach incorporates uncertainty in both numerical and graphical form. Some of the benefits of risk analysis are as follows:
Minimizing management crisis
Minimizing problems within the project lifecycle
Increase the likelihood of project success.
The case study in the next section demonstrates the importance of risk management within the construction industry.
1.8: Case Study: Sydney Opera House
Sidney Opera House is a construction project that cost the State government of New South Wales approximately $102 Million. The Opera House contains approximately 1000 rooms as well as the reception hall, four restaurants, extensive foyers and bars. Typically, many of the world best-known construction companies participated in the project, and it took the government 14 years to complete the project. Before the project was completed, several project risks emanated during the project lifecycle; one of the risks was the costs escalation that drove up the construction budget. Initial budget for the Sydney Opera House construction was $7.2 Million. However, with consistent cost escalation, the final costs used to complete the project were $102 Million. The government did not envisage that there could be increase in the costs during the project life cycle; however, the government used the state lotteries to cover the costs. Apart from the costs escalation that led to the increase in project budget, other risks identified in the project was design errors and omission. In the project design, the roof was too heavy to support the columns. The issues led some part of the building to be demolished and rebuilt. While the construction was initially planned to be completed within 5 years with the costs of $7.2 Million, however, risks associated with the project escalated the project costs to $102 Million and the project approximately took 14 years to complete. Total risks identified leading to the escalation of the project costs and elongation of the project due date are:
Poor cost estimate.
Incomplete design.
Failure to keep within the cost
Failure to stick to the required due date.
Changes in project requirements and scope.
Design changes.
Pressure from stakeholders to deliver project at quicker time.
Inaccurate contract time estimate
Lack of communication among project stakeholders.
Inadequately defined responsibilities.
Insufficient skilled manpower.
Political risks. (Eid, 2007).
1.9: Recommendations for Improvement
One of the best methods to manage risks in the construction project is to implement project risks plan before the implementation of the project. The risk plan should be used to identify different risks that could emanate during the project lifecycle. Identification of risks will enhance the strategy to manage the risks. Project stakeholders should categorize the risks based on their impact. The low risks should be absorbed while the risks carrying severe impact should be transferred and the method to transfer such risks is to use third party agent or insurance company.
More importantly, there is a need to implement contingency plan to describe in detail the solution to manage the risks in case the problem arises. The contingency plan should be drawn in such a way to reduce the risks to acceptable level. Additionally, there is a need to use experienced and skilled personnel in the project construction. Experienced and skilled personnel are likely to quickly identify the risks when emanated and suggest the best method to manage the risks during construction project.
2: Future Work and Conclusion
There is a need for further research on the method to manage risks in a complex construction project since experience has revealed that there are multiple risks associated with the complex project. The study explores risk identification process within the construction project and the strategy to mange these risks. The study discusses risk identification, risk management and risk analysis. The study also provides a case study to demonstrate the importance of risk management within the construction industry.
References
BurtonShAw-Gunn, a.(2009). Risk and Financial Management in Construction. Asghate. UK.
Dey, P.K. (2002). Project Risk Management: A Combined Analytic Hierarchy Process and Decision Tree Approach. Cost Engineering.44(3):13-26.
Eid, K. (2007). Risk Anaysis Case Study. Article Base.
El-Gafy, M. (2008). Risk Analysis for Design-Build Construction Projects: A Simplified Approach. Illinois State University.USA.
IBM (2009). Data Management for Risk Management: The Importance of data-orientated systems. International Business Machine. Ltd.
Klemetti, a. (2006).Risk Management in Construction Project Networks. Helsinki University of Technology. Laboratory of Industrial Management.
U.S Department f Transportation (2007). Risk Assessment and Allocation for Highway Construction Management. Federal Highway Administration.USA.
5.4: Accept Bullring team accepted some risks; however, the company developed the effective cost and schedule strategies to manage these risks. For example, the company allotted sufficient fund to militate against risks associated with the project costs and schedule. Table 2 presents the compressive list all the risks deemed to affect the outcome of the Bullring project. Table 2: Associated Risks on the Project Cost Related Risks: Index Scores Tight project schedule 0.67 Design variations 0.49 Project variations from
(in its turn, the financial environment must be understood with reference to the wider economic situation.) Cost control is the activity which compares cost performance against the cost plan, adjusting one or the other dynamically by reference to the changing circumstances in the project's financial environment. (Hughes, 1991, p.1) 2. Time Control -. Timing is influenced by many environmental factors, but the client's attitude to the timing of the project
Anticipated Implementation Issues and Opportunities Effective risk management is crucial for ensuring project success. This is true for not only large, complex projects, but also small and less complex projects such as renovating the kitchen at one’s residence. Kitchen renovation is a project that may involve substantive expenditure, hence the need for proper identification and mitigation of the associated risks. To this end, it is acknowledged that the major risks associated
Project Management, Sustainability and Whole Lifecycle Thinking ITT Project Management - Sustainability and Whole Lifecycle Thinking Although the sustainability movement has been advocated predominately in response to the irresponsible expansion of inefficient infrastructure by industrialized nations, with the United States and Japan now making significant efforts to embrace "green" growth practices, a growing movement has emerged that promoting sustainability throughout developing nations presents the most productive path. Even as the most modernized
. . political and law enforcement cronyism and corruption. . . And last, an surprising astonishing level of incompetence which symbolizes much of the authorized intelligence- meeting and investigative developments (Block, 1985, p.310). This lack of enforcement taking part in helping with the waste especially after a natural disaster such as a tornado will possibly allow such practices as illegal dumping to last unchecked. "The ideal answer to hazardous waste problems
Improving Project Performance Through Partnering and Emotional Intelligence The value of project management in achieving profitability goals is greatly enhanced when project managers utilize Emotional Intelligence (EI) in their management activities. EI is a great tool for partnering with project leaders and workers because it allows the individual to identify and respond to the sometimes subtle but present emotional needs of colleagues and contractors, which can range from a simple desire
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now