Such alerts would allow Sound Transit time to apply extra grout between the tunnel and the apartment building's basement.

6. Output Analysis and Discussion

Here, Sound Transit has taken reasonable and economically feasible precautions to reduce the risk of damage from soil sliding. At this point, the remaining hazards come from uncontrollable environmental factors, such as earthquakes and heavy rainfall, all of which are known to cause landslides and mudslides in the city of Seattle. Another factor which could cause damage to surface property is contractor negligence, for example when a contractor drills in a manner or pace which cumulates in excessive vibration and stress on surface structures.

7. Recommendation of the Improvement

In order to mitigate against uncontrollable environmental factors, Sound Transit should make sure that it has insurance policies which cover "Acts of God" in the event that such events result in property damage. In order to mitigate against contractor negligence, Sound Transit should create procedural guidelines which require regular measurement of soil impact and statements detailing contractor responses to new developments in soil conditions.

Bibliography

Practical Risk Management...

...

ent 4
PRM 4

http://projects.soundtransit.org/Projects-Home/University-Link.xml; http://projects.soundtransit.org/x1698.xml http://projects.soundtransit.org/Projects-Home/University-Link/Capitol-Hill-Station.xml

University Link fact sheet, available at http://projects.soundtransit.org/Documents/pdf/projects/link/north/ULink/U-LinkFact201105.pdf; Tunnel Boring Machine (TBM) fact sheet, available at http://projects.soundtransit.org/Documents/pdf/projects/link/north/ULink/Fact_TBM_2011.pdf

PRM5-6

PRM 6

http://seattletransitblog.com/2009/08/22/what-worries-me / http://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=4&ved=0CDgQFjAD&url=http%3A%2F%2seattletimes.nwsource.com%2Fhtml%2Flocalnews%2F2017786224_lightrailtunnel19m.html&ei=RcihT5uiItDXiQKY_KCnBw&usg=AFQjCNEXOMa_1eXjDZYHLmE0x17HwocskQ&sig2=foo46kTqgFccdURytNg8Aw

http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html

PRM 6

PRM 17

http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html

RISC 7

RISC 7

http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html?

Sources Used in Documents:

Bibliography

Practical Risk Management 4

PRM 4

http://projects.soundtransit.org/Projects-Home/University-Link.xml; http://projects.soundtransit.org/x1698.xml http://projects.soundtransit.org/Projects-Home/University-Link/Capitol-Hill-Station.xml

University Link fact sheet, available at http://projects.soundtransit.org/Documents/pdf/projects/link/north/ULink/U-LinkFact201105.pdf; Tunnel Boring Machine (TBM) fact sheet, available at http://projects.soundtransit.org/Documents/pdf/projects/link/north/ULink/Fact_TBM_2011.pdf
http://seattletransitblog.com/2009/08/22/what-worries-me / http://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=4&ved=0CDgQFjAD&url=http%3A%2F%2seattletimes.nwsource.com%2Fhtml%2Flocalnews%2F2017786224_lightrailtunnel19m.html&ei=RcihT5uiItDXiQKY_KCnBw&usg=AFQjCNEXOMa_1eXjDZYHLmE0x17HwocskQ&sig2=foo46kTqgFccdURytNg8Aw
http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html
http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html
http://seattletimes.nwsource.com/html/localnews/2017786224_lightrailtunnel19m.html?


Cite this Document:

"Construction Risk Management Of Channel" (2012, May 03) Retrieved April 27, 2024, from
https://www.paperdue.com/essay/construction-risk-management-of-channel-57113

"Construction Risk Management Of Channel" 03 May 2012. Web.27 April. 2024. <
https://www.paperdue.com/essay/construction-risk-management-of-channel-57113>

"Construction Risk Management Of Channel", 03 May 2012, Accessed.27 April. 2024,
https://www.paperdue.com/essay/construction-risk-management-of-channel-57113

Related Documents

Construction Project Proposal for a New Custom-Designed Hillside Home and PatioIntroductionA construction project proposal for a new custom-designed hillside home and patio that should take 12 months to complete is presented. The overview of the project includes a description of the work to be completed, the location of the project, the timeline for completion, and the staffing requirements. The costs associated with the project are also described, including the costs

The project manager should at all times be present to monitor and ensure that it's the correct mixing of materials being done, it's the right quality of material being used, and it's the right amount of time being given to the treatment process in the different construction phases. In the event that this is not observed, and the building is erected, there's a high probability that the building will

Effective risk management is crucial for ensuring project success. This is true for not only large, complex projects, but also small and less complex projects such as renovating the kitchen at one’s residence. Kitchen renovation is a project that may involve substantive expenditure, hence the need for proper identification, analysis, and mitigation of the associated risks. Generally, the major risks that may arise during the renovation of the kitchen relate

Anticipated Implementation Issues and Opportunities Effective risk management is crucial for ensuring project success. This is true for not only large, complex projects, but also small and less complex projects such as renovating the kitchen at one’s residence. Kitchen renovation is a project that may involve substantive expenditure, hence the need for proper identification and mitigation of the associated risks. To this end, it is acknowledged that the major risks associated

Furthermore, the proper selection of the team provides a means of determining general responsibilities for each team member involved. They will need to know the overall scope of their service while also knowing their overall design responsibilities as compared to their peers. In addition, their contracts will be a directly correlated to the contract and specifications of the client involved. This is important as it aligns the motivations of

S. DHS "Strategic Plan," 2008, http://www.dhs.gov/xabout/strategicplan/) Realistically acts of terrorism, domestic or foreign are exceedingly rare, though slightly more common than they have been in the past and at least marginally more violent in nature, they occur very, very rarely. (Lewis, 2000, p. 201) Though maintaining serious preparedness the mitigation of natural disasters, most which cannot be avoided is an issue needed to be addressed almost yearly, on both small