Skip to main content
Case Study Undergraduate 752 words

Healthcare.gov Contract Failure: A GAO Case Study

~4 min read
Abstract

This paper examines the government contracting failures behind the troubled 2013 launch of healthcare.gov, drawing on a GAO investigation (GAO-14-694). The Centers for Medicare and Medicaid Services (CMS) issued task orders before key technical requirements were established and relied on cost-reimbursement contracts that removed financial incentives for contractors to control costs or meet deadlines. The resulting cost overruns, schedule slips, and delayed functionality—compounded by inadequate oversight and deferred governance reviews—produced a website that launched without verified performance standards. The paper argues that the technical failure had broader consequences, eroding public trust in the Affordable Care Act itself and underscoring the need for rigorous contract management practices in government technology projects.

Key Takeaways
  • Introduction: The Healthcare.gov Crisis: Overview of the 2013 healthcare.gov launch failure
  • CMS Contracting Decisions and Structural Risk: How cost-reimbursement contracts created financial risk
  • Cost Overruns, Schedule Slips, and Oversight Gaps: GAO findings on delays and governance failures
  • Security, Usability, and Public Relations Fallout: Subcontractor failures and public trust erosion
  • Lessons Learned and Recommendations: Best practices needed for future government contracts
✍️ How to write this paper — guide, tools & examples

What makes this paper effective

  • Anchors its analysis in a specific, credible primary source — the GAO report (GAO-14-694) — giving the argument an authoritative evidentiary foundation.
  • Connects the technical and contractual failures to real-world consequences, demonstrating an understanding that government contracting breakdowns have political and social dimensions beyond their immediate operational scope.
  • Maintains a clear cause-and-effect structure: poor contracting decisions → misaligned incentives → cost and schedule failures → public trust erosion.

Key academic technique demonstrated

The paper uses a single in-depth case study to illustrate broader principles of government contract management. By tracing how a specific structural choice — the cost-reimbursement contract — created downstream incentive problems, the paper models how policy analysis moves from observable facts to systemic critique. This is a strong example of using a real-world case to test and apply theoretical frameworks in public administration.

Structure breakdown

The paper opens by contextualizing the healthcare.gov launch failure within the policy debate around the ACA, then narrows to the specific contracting decisions made by CMS. It draws directly on GAO findings to document cost overruns and governance failures before addressing the broader usability, security, and public relations consequences. The paper closes with a brief prescriptive recommendation emphasizing best practices and subcontractor oversight — giving it a complete problem-analysis-solution arc appropriate for a graduate-level policy case study.

Introduction: The Healthcare.gov Crisis

One of the most prominent government contracting failures of 2013–2014 was the healthcare.gov crisis. Healthcare.gov, the Internet exchange on which people could purchase healthcare plans on the open market, was largely inoperable during the first months of its existence. The fact that the website's dysfunction was fundamentally the result of a failed government contract is often overlooked, due to the intense focus on the policy debate surrounding the requirement that all American citizens obtain health insurance. A subsequent investigation by the Government Accountability Office examined the contract between the federal government and the Centers for Medicare and Medicaid Services (CMS), the agency charged with designing and overseeing the website.

CMS Contracting Decisions and Structural Risk

According to the GAO investigation, "to be expedient, CMS issued task orders to develop the federally facilitated marketplace (FFM) and federal data services hub (data hub) systems when key technical requirements were unknown, including the number and composition of states to be supported and, importantly, the number of potential enrollees. CMS used cost-reimbursement contracts, which created additional risk because CMS is required to pay the contractor's allowable costs regardless of whether the system is completed" ("Ineffective Planning," 2014).

This structural decision — awarding contracts before foundational technical requirements were established — set the stage for cascading failures. The GAO report (GAO-14-694) identified this as a critical early misstep that undermined the entire project from the outset. By committing to cost-reimbursement contracts under conditions of significant uncertainty, CMS effectively eliminated the financial incentives that might otherwise have encouraged contractors to control spending and adhere to deadlines.

Cost Overruns, Schedule Slips, and Oversight Gaps

The result was that costs spiraled out of control along with the project timeline. Without an incentive to contain costs — given the requirement that all of the contractors' allowable expenses be covered — subcontractors adopted a notably relaxed attitude toward deadlines. This proved particularly damaging given the legally mandated date by which all Americans were required to have purchased some form of health insurance.

Over the course of the project, "CMS incurred significant cost increases, schedule slips, and delayed system functionality for the FFM and data hub systems due primarily to changing requirements that were exacerbated by oversight gaps. New requirements and changing CMS decisions also led to delays and wasted contractor efforts. Moreover, CMS delayed key governance reviews, moving an assessment of FFM readiness from March to September 2013 — just weeks before the launch — and did not receive required approvals. As a result, CMS launched healthcare.gov without verification that it met performance requirements" ("Ineffective Planning," 2014).

The deferral of the readiness assessment to just weeks before launch, combined with the absence of required approvals, represents a significant failure of federal procurement oversight. These governance gaps compounded the technical shortcomings already embedded in the project through its flawed contracting structure.

2 locked sections · 170 words
Sign up to read the full analysis
Security, Usability, and Public Relations Fallout90 words
CMS employed a series of subcontractors whose work was ultimately found to be questionable and contributed directly to the website's failure. However, CMS's own lackadaisical attitude toward quality control was, in many…
Lessons Learned and Recommendations80 words
Healthcare.gov taught a powerful lesson about the role of technology in the modern Internet age: usability and reliability for a government website are essential — without them, the public may lose trust not just in the website but in the law it represents. The failure of the site had repercussions that extended far beyond…
Read the full paper →
Plus 130,000+ examples & all writing tools

References

Ineffective planning and oversight practices underscore the need for improved contract management. (2014). GAO-14-694. Retrieved from

Key Concepts in This Paper
Government Contracting Cost-Reimbursement CMS Oversight Healthcare.gov GAO Audit Subcontractor Risk Schedule Slips Public Trust ACA Implementation Contract Management
Cite This Paper
PaperDue. (2026). Healthcare.gov Contract Failure: A GAO Case Study. PaperDue. https://www.paperdue.com/study-guide/healthcare-gov-contract-failure-gao-case-study-191271

Always verify citation format against your institution’s current style guide requirements.