Skip to main content
Research Paper Undergraduate 3,074 words

Building Construction Analysis: Footing, Floor & Site Prep

~16 min read
Abstract

This paper provides a technical analysis of a residential building construction project observed across multiple stages. It covers site preparation and excavation, footing design using reinforced concrete strip footings and waffle slabs, and the slab-on-ground floor system. The paper outlines the construction sequence for footings and floor installation in accordance with Australian Standards (AS2870, AS3660.1), addresses soil classification for the Sydney site (Class S, slightly reactive black clay), and evaluates the suitability of the concrete floor system chosen. It also compares the concrete floor system against a suspended timber floor alternative across parameters including installation, termite protection, insulation, sustainability, cost, and construction trades involved.

Key Takeaways
  • Site Preparation and Excavation: Demolition, grading, leveling, and equipment used
  • Footing System Construction: Strip footings, piers, waffle slabs, and vapor barriers
  • Floor System Installation: Slab-on-ground, termite control, and concrete pouring
  • Construction Sequence and Concrete Requirements: Step-by-step footing, slab, and surface construction process
  • Soil Classification and Footing Suitability: Class S black clay soil and footing design rationale
  • Concrete vs. Suspended Timber Floor: A Comparative Analysis: Multi-criteria comparison of two floor system alternatives
✍️ How to write this paper — guide, tools & examples

What makes this paper effective

  • Grounded in specific Australian Standards (AS2870, AS3660.1), giving every procedural claim a verifiable regulatory basis.
  • Moves logically from site observation to technical description to comparative evaluation, demonstrating applied rather than purely theoretical knowledge.
  • The comparative section in Task 4 uses consistent evaluative criteria across both floor systems, making the final justification of the concrete system persuasive and well-supported.

Key academic technique demonstrated

The paper demonstrates evidence-based technical justification: each construction decision (choice of footing type, slab system, termite strategy) is linked explicitly to a standard, guideline, or cited authority rather than stated as general practice. This anchoring of observations to regulatory and scholarly sources is the hallmark of professional technical writing in construction contexts.

Structure breakdown

The paper is organized into four tasks mirroring a professional site-analysis report. Task 1 describes observable construction stages with supporting figures and bullet-point observables. Task 2 provides a numbered construction sequence with concrete-casting requirements. Task 3 addresses soil classification and footing suitability for the specific site conditions. Task 4 delivers a multi-criteria comparison of floor system alternatives and justifies the chosen concrete approach. Each task builds on the previous one, moving from description to prescription to evaluation.

Site Preparation and Excavation

In all construction and building projects, site clearing is the initial phase. It involves the removal of trees, vegetation, and old or unwanted structures from the prospective site, as was the case in the observed project. In accordance with Wilkie (2011), all services including water, gas, and power were disconnected from the structure before demolition work began. Other services such as drainage and stormwater were also sealed off, and the necessary steps were taken to ensure that nearby properties were protected. One of these strategies was to fence the site and ensure appropriate barricading to prevent unauthorized access (Wilkie 2011). After demolition, the rubble was cleared and excavation work began.

Various equipment can be used in the excavation phase, and the choice depends on the nature of the specific site. For this project, site preparation and excavation were carried out using an excavator, semi-trucks, a Bobcat, vertical rammers, tippers, and plate compactors (Department of Training and Workforce Development 2012). All equipment was operated by trained professionals to ensure the safety of everyone involved and that work was completed to the required standards.

To ensure the site was completely level and that erosion and runoff were controlled, Bobcats were used to level and grade the construction site. Grading is vital on a construction site because it helps to avert water flow through the site and provides a stable base for the foundation of a newly built structure. Grading on this site was achieved by creating a slope away from the foundation (Department of Justice 2017). The ground was also leveled to ensure a perfectly level base for the foundation, using a builder's auto-level, commonly known as the dumpy level.

Observables — Site Preparation:

Footing System Construction

The role of the footing is to carry the structure, form a base for the foundation, and transmit the superimposed load of the structure to the ground. According to Wilkie (2011) and the Department of Justice (2017), the type and size of materials should be proportionate enough to bear the load and suited to the condition of the soil. In the current construction project, excavation of the footings was carried out using an excavator. Piers were also used, with holes dug using an excavator fitted with an auger bit attachment. Reinforced concrete was used for the footings.

After the footing, the slab was laid. A plastic sheet was used as a vapor barrier to prevent water from rising from the ground into the slab (Department of Justice 2017). This was in line with AS 2870:2011 Residential Slabs and Footings, clause 5.3.3.2(c), which requires that vapor barriers be medium impact resistant. A strip footing was used that follows the structure's walls — both external and internal — thereby uniformly distributing the load throughout the structure. Both the strip footing and the slab were reinforced with steel beams.

In addition to the reinforced concrete used for the footing and slab, waffle slabs were also incorporated. The waffle slabs were shipped to the site in prefabricated form, placed in waffle pods, and connected using ribbed columns along the slab. Waffle pods consisted of equally spaced ribs with corresponding columns. A two-way ribbed system of waffle slab pods was reinforced with concrete cross-sections comprising ribbed reinforcement, slab top wire mesh, void depth and width, and overall waffle slab thickness (Galeb and Atiyah 2011).

Observables — Footing:

Floor System Installation

Piers were used to support the concrete slab-and-beam floor. Pier holes were excavated along the location of the planned structural walls to carry the load of the structure and transfer it effectively to the ground. The excavated piers had concrete poured into them, and a slab-and-beam floor system was then cast on a compressible void-former that provides space for soil expansion (Standards Australia 2011). The piers were made of concrete and treated timber, set to an appropriate depth and then cut at the desired level to allow for the casting of the floor.

As required by AS 3660.1, termite control systems were employed in this building project. Multiple termite control methods were used, including chemical treatment and physical barriers such as graded stone particles and woven stainless steel wire mesh. The footing and slab also incorporated termite prevention elements, most notably the use of tight slab concrete.

A slab-on-ground type was selected for this structure. To make the slab firm and well anchored, adequately excavated beams were used. Waffle slabs placed near ground level were used with a grid of polystyrene foam void formers that create a beam maze between the pods (Standards Australia 2011; Department of Justice 2017). Insulation, as required with conventional slabs, is placed beneath the floor panels — in this building, below the waffle slab pods.

Because the site was level, laying the various floor elements was straightforward. After the ground was adequately compacted with a layer of gravel, plumbing was installed, termite treatment was carried out, and the outside edge boards were set in place. The entire area within the edge boards was covered with plastic sheeting, followed by a layer of wire mesh. Waffle pods and spacers were then placed in a grid pattern as specified in AS2870 (Standards Australia 2011). Steel reinforcement beams were placed within the spacers between the waffle pods, and a wire mesh layer was placed on top. The top wire mesh and reinforcement beams were fastened as required, then concrete mix was poured and adequately vibrated. The floor was finished by applying a thin top layer of colored cement and sand, with the color varying by room — for example, violet was used for the bedrooms.

Observables — Flooring:

3 locked sections · 1,200 words
Sign up to read the full analysis
Construction Sequence and Concrete Requirements420 words
To ensure safe and high-quality concrete works, the following requirements must be observed:
Soil Classification and Footing Suitability220 words
According to Australian building standards, knowledge of the soil is essential when building a structure. Essential features of the soil include its chemical and physical properties,…
Concrete vs. Suspended Timber Floor: A Comparative Analysis560 words
The current building uses a solid ground concrete floor system. One alternative is the suspended timber floor. A suspended timber floor…
Read the full paper →
Plus 130,000+ examples & all writing tools

References

Australian Safety and Compensation Council (ASCC), 2008. National Code of Practice for Precast, Tilt-Up and Concrete Elements in Building Construction. Commonwealth of Australia.

Barrie, D.S. and Paulson, B.C., 1992. Professional Construction Management: Including CM, Design-Construct, and General Contracting. McGraw-Hill.

Building and Development, 2016. Termite Protection Guide: Protection from Beneath Concrete Slabs — AS 3660.1. Hawkesbury City Council.

Charman, P.E. and Murphy, B.W. eds., 2007. Soils: Their Properties and Management. Oxford University Press.

Clarke, D., 2013. Concrete slab floors, Yourhome.

Department of Justice, 2017. Guide to Standards and Tolerances 2017. Consumer, Building and Occupational Services.

Department of Training and Workforce Development, 2012. Undertake Application of Building Codes and Standards to Residential Buildings.

Ewart, D.M., 2001. Termite barriers for new construction in Australia (Isoptera). Sociobiology, 37(2), pp. 379–388.

Galeb, A.C. and Atiyah, Z.F., 2011. Optimum design of reinforced concrete waffle slabs. International Journal of Civil and Structural Engineering, 1(4), p. 862.

Isbell, R., 2016. The Australian Soil Classification. CSIRO Publishing.

Olubunmi, O.A., Olaniyi, A.I. and Fisayo, A., 2014. Diversity among construction professionals: A study of their perception of construction site management practices. Organization, Technology & Management in Construction, 6(2).

Ortiz, O., Castells, F. and Sonnemann, G., 2009. Sustainability in the construction industry: A review of recent developments based on LCA. Construction and Building Materials, 23(1), pp. 28–39.

Pelsmakers, S. and Elwell, C.A., 2017. Suspended timber ground floors: Heat loss reduction potential of insulation interventions. Energy and Buildings, 153, pp. 549–563.

Prescott, J.A., 1931. The Soils of Australia in Relation to Vegetation and Climate. Council for Scientific and Industrial Research.

Smith, T., Fragiacomo, M., Pampanin, S. and Buchanan, A.H., 2009. Construction time and cost for post-tensioned timber buildings. Proceedings of the Institution of Civil Engineers — Construction Materials, 162(4), pp. 141–149.

Standards Australia, 2011. AS2870:2011 Residential Slabs and Footings.

Standards Australia, 2013. Guide to Standards — Building and Construction. SAI Global.

Thomas, D. and Ding, G., 2018. Comparing the performance of brick and timber in residential buildings — the case of Australia. Energy and Buildings, 159, pp. 136–147.

WA Department of Communities, 2017. Housing — NATSPEC Construction Specification: Prefabricated Housing.

Wilkie, G., 2011. Building Your Own Home: A Comprehensive Guide for Owner-Builders. New Holland Publishers.

Key Concepts in This Paper
Strip Footing Waffle Slab Slab-on-Ground Soil Classification Termite Protection Reinforced Concrete Site Preparation Suspended Timber Floor AS2870 Standard Vapor Barrier Concrete Casting Floor Insulation
Cite This Paper
PaperDue. (2026). Building Construction Analysis: Footing, Floor & Site Prep. PaperDue. https://www.paperdue.com/study-guide/building-construction-footing-floor-analysis-2177635

Always verify citation format against your institution’s current style guide requirements.